EstatePass
Contract AdminProcedureshard13% of exam part

A project has a total duration of 120 days. If the critical path is compressed by 10 days through crashing activities at an additional cost of $25,000, and the daily overhead cost is $800, what is the net cost impact?

Correct Answer

D) $17,000 cost

Crashing cost is $25,000, but overhead savings from 10 fewer days is 10 × $800 = $8,000. Net cost impact is $25,000 - $8,000 = $17,000 additional cost.

Answer Options
A
$25,000 cost
B
$8,000 savings
C
$33,000 cost
D
$17,000 cost

Why This Is the Correct Answer

When crashing a project, you must consider both the additional costs of crashing activities and the savings from reduced overhead costs. The crashing cost is $25,000, but compressing the schedule by 10 days saves $8,000 in daily overhead (10 days × $800/day). The net cost impact is the difference between these amounts: $25,000 - $8,000 = $17,000 additional cost.

Why the Other Options Are Wrong

Option A: $25,000 cost

This option incorrectly adds the crashing cost and overhead savings ($25,000 + $8,000 = $33,000), when the overhead savings should be subtracted from the crashing cost.

Option C: $33,000 cost

This option only considers the crashing cost of $25,000 but fails to account for the overhead savings of $8,000 from the 10-day schedule compression.

Memory Technique

Remember 'CRASH minus CASH' - Crashing costs minus overhead Cash savings equals net impact

Reference Hint

Project Management chapter covering Critical Path Method (CPM) and schedule compression techniques including crashing and fast-tracking

Was this explanation helpful?

More Contract Admin Questions

A project experiences a 30-day delay due to unusually severe weather. The contract includes a liquidated damages clause of $1,000 per day for delays. If the weather delay is excusable but not compensable, what liquidated damages apply?

A commercial project requires a total of 12 inspections. The building department charges $85 per inspection for the first 5 inspections, $65 for inspections 6-10, and $45 for any additional inspections. What is the total inspection fee?

What document must be posted at the job site before a Certificate of Occupancy can be issued for a commercial building?

A mixed-use development requires a variance for reduced setbacks. The property is located within 500 feet of a hospital. What additional consideration must be addressed?

A LEED project requires tracking of regional materials. Materials are considered regional if they are extracted, harvested, or recovered, as well as manufactured within what distance of the project site?

An indemnification clause in a construction contract typically requires the contractor to:

A property owner wants to convert a single-family home into a duplex in an area zoned for single-family residential use. The conversion meets all building codes but violates density requirements. What approval is needed?

As-built drawings are typically required to be submitted:

AIA Document A401 is primarily used for:

A general contractor is building a 12,000 square foot commercial warehouse. The building permit fee is calculated at $8.50 per $1,000 of construction value. If the project value is $2,400,000, what is the building permit fee?

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your Florida General Contractor exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.