EstatePass
Contract AdminPreconstructionmedium27% of exam part

A contractor receives the following bids for sitework: $125,000, $118,000, $145,000, and $95,000. The engineer's estimate was $130,000. Which bid should receive the most scrutiny?

Correct Answer

B) $95,000 - significantly below others

The $95,000 bid is significantly below the engineer's estimate and other bids, suggesting possible errors, omissions, or unrealistic pricing that could lead to problems during construction.

Answer Options
A
$125,000 - closest to engineer's estimate
B
$95,000 - significantly below others
C
$118,000 - reasonable and competitive
D
$145,000 - highest bid received

Why This Is the Correct Answer

The $95,000 bid is approximately 27% below the engineer's estimate and 19% below the next lowest bid, which represents a significant deviation that warrants investigation. Such a large variance typically indicates potential errors in the bid calculation, missing scope items, or unrealistic pricing that could lead to change orders, delays, or contractor financial difficulties during construction. As a general contractor, scrutinizing unusually low bids protects against future project complications and ensures the subcontractor can actually perform the work as specified.

Why the Other Options Are Wrong

Option A: $125,000 - closest to engineer's estimate

While the $125,000 bid is closest to the engineer's estimate, being close to the estimate doesn't necessarily require additional scrutiny - it suggests the bid is reasonable and well-calculated.

Option D: $145,000 - highest bid received

The $118,000 bid is within a reasonable range of the engineer's estimate (about 9% lower) and falls between other competitive bids, making it appear legitimate and not requiring special scrutiny.

Memory Technique

Use 'LOW = LOOK OUT WIDE' - when a bid is significantly LOW, LOOK OUT for problems and investigate WIDE-ranging potential issues

Reference Hint

Florida Building Code - Administration and Enforcement, Chapter on Contract Administration and Bidding Procedures

Was this explanation helpful?

More Contract Admin Questions

A project experiences a 30-day delay due to unusually severe weather. The contract includes a liquidated damages clause of $1,000 per day for delays. If the weather delay is excusable but not compensable, what liquidated damages apply?

A commercial project requires a total of 12 inspections. The building department charges $85 per inspection for the first 5 inspections, $65 for inspections 6-10, and $45 for any additional inspections. What is the total inspection fee?

What document must be posted at the job site before a Certificate of Occupancy can be issued for a commercial building?

A mixed-use development requires a variance for reduced setbacks. The property is located within 500 feet of a hospital. What additional consideration must be addressed?

A LEED project requires tracking of regional materials. Materials are considered regional if they are extracted, harvested, or recovered, as well as manufactured within what distance of the project site?

An indemnification clause in a construction contract typically requires the contractor to:

A property owner wants to convert a single-family home into a duplex in an area zoned for single-family residential use. The conversion meets all building codes but violates density requirements. What approval is needed?

As-built drawings are typically required to be submitted:

AIA Document A401 is primarily used for:

A general contractor is building a 12,000 square foot commercial warehouse. The building permit fee is calculated at $8.50 per $1,000 of construction value. If the project value is $2,400,000, what is the building permit fee?

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your Florida General Contractor exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.