EstatePass
Contract AdminContractsmedium40% of exam part

A contractor receives a Notice to Owner from a subcontractor 23 days after the subcontractor first provided materials to the project. Under Florida law, is this notice valid?

Correct Answer

D) Yes, it meets the 45-day requirement

Under Florida Statute 713.06, a Notice to Owner must be served within 45 days of first providing labor or materials to the project. Since 23 days is within this timeframe, the notice is valid and preserves the subcontractor's lien rights.

Answer Options
A
No, it was served too late
B
Yes, but only for materials provided after the notice date
C
No, only the general contractor can serve this notice
D
Yes, it meets the 45-day requirement

Why This Is the Correct Answer

Under Florida Statute 713.06, subcontractors must serve a Notice to Owner within 45 days of first providing labor, services, or materials to improve real property. The subcontractor in this scenario served the notice after 23 days, which is well within the 45-day statutory requirement. This timely notice preserves the subcontractor's right to claim a construction lien for all work performed on the project, both before and after the notice date.

Why the Other Options Are Wrong

Option A: No, it was served too late

This is incorrect because 23 days falls well within the 45-day statutory deadline established by Florida Statute 713.06. The notice was served timely, not too late.

Option C: No, only the general contractor can serve this notice

This is incorrect because subcontractors are specifically required and authorized to serve Notice to Owner under Florida lien law. In fact, it's the subcontractor's responsibility, not the general contractor's, to protect their own lien rights through proper notice.

Memory Technique

Remember '45 and Alive' - subcontractors have 45 days to serve Notice to Owner to keep their lien rights alive and preserve their right to payment.

Reference Hint

Florida Statutes Chapter 713 - Construction Liens, specifically Section 713.06 regarding Notice to Owner requirements and timing

Was this explanation helpful?

More Contract Admin Questions

A project experiences a 30-day delay due to unusually severe weather. The contract includes a liquidated damages clause of $1,000 per day for delays. If the weather delay is excusable but not compensable, what liquidated damages apply?

A commercial project requires a total of 12 inspections. The building department charges $85 per inspection for the first 5 inspections, $65 for inspections 6-10, and $45 for any additional inspections. What is the total inspection fee?

What document must be posted at the job site before a Certificate of Occupancy can be issued for a commercial building?

A mixed-use development requires a variance for reduced setbacks. The property is located within 500 feet of a hospital. What additional consideration must be addressed?

A LEED project requires tracking of regional materials. Materials are considered regional if they are extracted, harvested, or recovered, as well as manufactured within what distance of the project site?

An indemnification clause in a construction contract typically requires the contractor to:

A property owner wants to convert a single-family home into a duplex in an area zoned for single-family residential use. The conversion meets all building codes but violates density requirements. What approval is needed?

As-built drawings are typically required to be submitted:

AIA Document A401 is primarily used for:

A general contractor is building a 12,000 square foot commercial warehouse. The building permit fee is calculated at $8.50 per $1,000 of construction value. If the project value is $2,400,000, what is the building permit fee?

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your Florida General Contractor exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.