If a project has liquidated damages of $500 per day and is completed 15 days late, what amount can the owner deduct from the final payment?
Correct Answer
B) $7,500
Liquidated damages calculation: $500 per day × 15 days late = $7,500 that can be deducted from the contractor's final payment.
Why This Is the Correct Answer
Liquidated damages are predetermined amounts specified in the contract that the contractor must pay for each day the project is completed late. The calculation is straightforward multiplication: the daily rate multiplied by the number of late days. In this case, $500 per day × 15 days = $7,500. This amount represents the owner's compensation for damages caused by the delay and can be legally deducted from the contractor's final payment.
Why the Other Options Are Wrong
Option A: $6,500
$6,500 would result from multiplying $500 × 13 days, which uses the wrong number of late days
Option C: $8,000
$8,000 would result from multiplying $500 × 16 days, which overstates the delay period by one day
Option D: $7,000
$7,000 would result from multiplying $500 × 14 days, which is one day short of the actual 15-day delay
Memory Technique
Remember 'LID' - Liquidated damages = Late days × Initial daily rate. The formula is always: Daily Rate × Number of Late Days = Total Deduction
Reference Hint
Look up 'Liquidated Damages' in the contract law section or Chapter 713 Florida Statutes regarding construction liens and contract remedies
More Contract Admin Questions
A project experiences a 30-day delay due to unusually severe weather. The contract includes a liquidated damages clause of $1,000 per day for delays. If the weather delay is excusable but not compensable, what liquidated damages apply?
A commercial project requires a total of 12 inspections. The building department charges $85 per inspection for the first 5 inspections, $65 for inspections 6-10, and $45 for any additional inspections. What is the total inspection fee?
What document must be posted at the job site before a Certificate of Occupancy can be issued for a commercial building?
A mixed-use development requires a variance for reduced setbacks. The property is located within 500 feet of a hospital. What additional consideration must be addressed?
A LEED project requires tracking of regional materials. Materials are considered regional if they are extracted, harvested, or recovered, as well as manufactured within what distance of the project site?
An indemnification clause in a construction contract typically requires the contractor to:
A property owner wants to convert a single-family home into a duplex in an area zoned for single-family residential use. The conversion meets all building codes but violates density requirements. What approval is needed?
As-built drawings are typically required to be submitted:
AIA Document A401 is primarily used for:
A general contractor is building a 12,000 square foot commercial warehouse. The building permit fee is calculated at $8.50 per $1,000 of construction value. If the project value is $2,400,000, what is the building permit fee?
People Also Study
Business & Financial Management
120 questions · 70% to pass
Project Management
60 questions · 70% to pass
Related Study Resources
Previous Question
A contractor is estimating the cost to rent a crane for 45 days. The rental rate is $1,200 per day, but there is a monthly rate of $22,000. What is the most cost-effective option?
Next Question
A contractor receives a Notice to Owner from a subcontractor 23 days after the subcontractor first provided materials to the project. Under Florida law, is this notice valid?
