EstatePass
Contract AdminPreconstructionhard27% of exam part

A contractor is estimating the cost to rent a crane for 45 days. The rental rate is $1,200 per day, but there is a monthly rate of $22,000. What is the most cost-effective option?

Correct Answer

C) Monthly rate: $44,000

Daily rate for 45 days: 45 × $1,200 = $54,000. Monthly rate for 2 months: 2 × $22,000 = $44,000. The monthly rate is more cost-effective even though it covers 60 days versus the needed 45 days.

Answer Options
A
Purchase the crane instead
B
Daily rate: $54,000
C
Monthly rate: $44,000
D
Combination of monthly and daily rates: $37,000

Why This Is the Correct Answer

Option B is correct because when comparing rental options, you must calculate the total cost for each viable option and choose the lowest. The daily rate for 45 days costs $54,000, while renting for 2 full months (60 days) at the monthly rate costs only $44,000. Even though the monthly option provides 15 extra days of rental, it's still $10,000 cheaper than the daily rate for exactly 45 days. This demonstrates that longer-term rental rates often provide better value even when you don't need the full duration.

Why the Other Options Are Wrong

Option A: Purchase the crane instead

Option D suggests purchasing instead of renting, but no purchase price information is provided in the problem, making this option impossible to evaluate or justify.

Option B: Daily rate: $54,000

Option A shows the daily rate calculation ($54,000) but this is the most expensive option, not the most cost-effective choice.

Option D: Combination of monthly and daily rates: $37,000

Option C suggests a combination approach costing $37,000, but this calculation is not supported by the given rental terms and appears to be an incorrect mathematical combination.

Memory Technique

Remember 'Monthly Means More savings' - longer rental periods typically offer better rates per day, even if you pay for unused time

Reference Hint

Construction project management and cost estimation chapters, specifically equipment rental and cost analysis sections

Was this explanation helpful?

More Contract Admin Questions

A project experiences a 30-day delay due to unusually severe weather. The contract includes a liquidated damages clause of $1,000 per day for delays. If the weather delay is excusable but not compensable, what liquidated damages apply?

A commercial project requires a total of 12 inspections. The building department charges $85 per inspection for the first 5 inspections, $65 for inspections 6-10, and $45 for any additional inspections. What is the total inspection fee?

What document must be posted at the job site before a Certificate of Occupancy can be issued for a commercial building?

A mixed-use development requires a variance for reduced setbacks. The property is located within 500 feet of a hospital. What additional consideration must be addressed?

A LEED project requires tracking of regional materials. Materials are considered regional if they are extracted, harvested, or recovered, as well as manufactured within what distance of the project site?

An indemnification clause in a construction contract typically requires the contractor to:

A property owner wants to convert a single-family home into a duplex in an area zoned for single-family residential use. The conversion meets all building codes but violates density requirements. What approval is needed?

As-built drawings are typically required to be submitted:

AIA Document A401 is primarily used for:

A general contractor is building a 12,000 square foot commercial warehouse. The building permit fee is calculated at $8.50 per $1,000 of construction value. If the project value is $2,400,000, what is the building permit fee?

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your Florida General Contractor exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.