In a unit price contract for 5,000 linear feet of fencing at $45 per linear foot, the actual quantity installed was 5,250 linear feet. What is the total contract amount?
Correct Answer
A) $236,250
In unit price contracts, payment is based on actual quantities installed. The total is calculated as 5,250 linear feet × $45 per linear foot = $236,250.
Why This Is the Correct Answer
In unit price contracts, the contractor is paid based on the actual quantities of work performed, not the estimated quantities in the original contract. Since 5,250 linear feet were actually installed, this becomes the basis for payment calculation. The total contract amount is determined by multiplying the actual quantity (5,250 LF) by the unit price ($45/LF), resulting in $236,250.
Why the Other Options Are Wrong
Option B: $247,500
This represents the original estimated contract amount (5,000 LF × $45 = $225,000) but fails to account for the additional 250 linear feet that were actually installed
Option C: $225,000
This represents 6,000 linear feet at $45 per linear foot, which significantly overstates the actual quantity installed by 750 linear feet
Memory Technique
Think 'ACTUAL PAYS' - in unit price contracts, you get paid for ACTUAL work performed, not estimated quantities
Reference Hint
Florida Building Code Chapter 1, Section 107 - Permits and Construction Documents, or contract administration sections in construction management references
More Contract Admin Questions
A project experiences a 30-day delay due to unusually severe weather. The contract includes a liquidated damages clause of $1,000 per day for delays. If the weather delay is excusable but not compensable, what liquidated damages apply?
A commercial project requires a total of 12 inspections. The building department charges $85 per inspection for the first 5 inspections, $65 for inspections 6-10, and $45 for any additional inspections. What is the total inspection fee?
What document must be posted at the job site before a Certificate of Occupancy can be issued for a commercial building?
A mixed-use development requires a variance for reduced setbacks. The property is located within 500 feet of a hospital. What additional consideration must be addressed?
A LEED project requires tracking of regional materials. Materials are considered regional if they are extracted, harvested, or recovered, as well as manufactured within what distance of the project site?
An indemnification clause in a construction contract typically requires the contractor to:
A property owner wants to convert a single-family home into a duplex in an area zoned for single-family residential use. The conversion meets all building codes but violates density requirements. What approval is needed?
As-built drawings are typically required to be submitted:
AIA Document A401 is primarily used for:
A general contractor is building a 12,000 square foot commercial warehouse. The building permit fee is calculated at $8.50 per $1,000 of construction value. If the project value is $2,400,000, what is the building permit fee?
People Also Study
Business & Financial Management
120 questions · 70% to pass
Project Management
60 questions · 70% to pass
