EstatePass
Contract AdminPreconstructionmedium27% of exam part

During bid evaluation, a contractor receives the following electrical subcontractor bids: $85,000, $92,000, $78,000, and $105,000. Which bid requires the most careful scrutiny?

Correct Answer

C) $78,000

The $78,000 bid is significantly lower than the others and requires careful scrutiny to ensure the bidder hasn't made errors, omitted items, or may be unable to perform the work profitably.

Answer Options
A
$92,000
B
$105,000
C
$78,000
D
$85,000

Why This Is the Correct Answer

The $78,000 bid is significantly lower than the other bids, representing a substantial deviation from the average bid amount. When a bid is unusually low compared to other qualified bidders, it raises red flags about potential calculation errors, missing scope items, or the subcontractor's ability to complete the work profitably. This low bid requires the most scrutiny to verify accuracy and feasibility before acceptance.

Why the Other Options Are Wrong

Option A: $92,000

While the $105,000 bid is the highest, it's not as concerning as an unusually low bid since high bids typically don't pose the same risks of incomplete work or contractor failure

Option B: $105,000

The $85,000 bid is close to the middle range of the bids received and doesn't represent an extreme deviation that would require special scrutiny

Option D: $85,000

The $92,000 bid falls within the reasonable range of the other bids and doesn't show any concerning patterns that would require additional investigation

Memory Technique

Think 'Too Low To Trust' - when a bid is significantly lower than others, it's too low to trust without thorough investigation

Reference Hint

Florida Building Code - Chapter 1, Administrative provisions regarding bid evaluation procedures and contractor qualification requirements

Was this explanation helpful?

More Contract Admin Questions

A project experiences a 30-day delay due to unusually severe weather. The contract includes a liquidated damages clause of $1,000 per day for delays. If the weather delay is excusable but not compensable, what liquidated damages apply?

A commercial project requires a total of 12 inspections. The building department charges $85 per inspection for the first 5 inspections, $65 for inspections 6-10, and $45 for any additional inspections. What is the total inspection fee?

What document must be posted at the job site before a Certificate of Occupancy can be issued for a commercial building?

A mixed-use development requires a variance for reduced setbacks. The property is located within 500 feet of a hospital. What additional consideration must be addressed?

A LEED project requires tracking of regional materials. Materials are considered regional if they are extracted, harvested, or recovered, as well as manufactured within what distance of the project site?

An indemnification clause in a construction contract typically requires the contractor to:

A property owner wants to convert a single-family home into a duplex in an area zoned for single-family residential use. The conversion meets all building codes but violates density requirements. What approval is needed?

As-built drawings are typically required to be submitted:

AIA Document A401 is primarily used for:

A general contractor is building a 12,000 square foot commercial warehouse. The building permit fee is calculated at $8.50 per $1,000 of construction value. If the project value is $2,400,000, what is the building permit fee?

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your Florida General Contractor exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.