EstatePass
Contract AdminContractseasy40% of exam part

What is the primary difference between a lump sum contract and a guaranteed maximum price (GMP) contract?

Correct Answer

B) GMP contracts allow cost savings to be shared while lump sum contracts provide a fixed price regardless of actual costs

A GMP contract establishes a ceiling price but typically includes provisions for sharing cost savings between owner and contractor, while a lump sum contract provides a fixed price regardless of the contractor's actual costs. Both contract types can be used on public or private projects.

Answer Options
A
Lump sum contracts require more detailed cost documentation than GMP contracts
B
GMP contracts allow cost savings to be shared while lump sum contracts provide a fixed price regardless of actual costs
C
GMP contracts can only be used on public projects while lump sum contracts are for private projects
D
Lump sum contracts include a fixed profit margin while GMP contracts do not

Why This Is the Correct Answer

Option B correctly identifies the fundamental difference between these contract types. A GMP contract sets a maximum price ceiling but typically includes cost-sharing provisions where any savings below the GMP are split between the owner and contractor according to predetermined percentages. In contrast, a lump sum contract establishes a fixed price that remains unchanged regardless of the contractor's actual costs - the contractor keeps all savings or absorbs all overruns. This cost-sharing mechanism is the key distinguishing feature that makes GMP contracts attractive to both parties.

Why the Other Options Are Wrong

Option A: Lump sum contracts require more detailed cost documentation than GMP contracts

This is incorrect because both contract types can include fixed profit margins. The profit structure is not the primary distinguishing factor between lump sum and GMP contracts.

Option C: GMP contracts can only be used on public projects while lump sum contracts are for private projects

This is incorrect because GMP contracts typically require more detailed cost documentation and tracking than lump sum contracts, since costs must be monitored to determine savings and calculate shared benefits.

Option D: Lump sum contracts include a fixed profit margin while GMP contracts do not

This is incorrect because both GMP and lump sum contracts can be used on either public or private projects. The project type does not determine which contract method can be used.

Memory Technique

Think 'GMP = Give Me Part' (of the savings) vs 'Lump Sum = Locked Sum' (no sharing, fixed regardless of actual costs)

Reference Hint

Florida Building Construction Standards - Chapter on Contract Types and Pricing Methods

Was this explanation helpful?

More Contract Admin Questions

A project experiences a 30-day delay due to unusually severe weather. The contract includes a liquidated damages clause of $1,000 per day for delays. If the weather delay is excusable but not compensable, what liquidated damages apply?

A commercial project requires a total of 12 inspections. The building department charges $85 per inspection for the first 5 inspections, $65 for inspections 6-10, and $45 for any additional inspections. What is the total inspection fee?

What document must be posted at the job site before a Certificate of Occupancy can be issued for a commercial building?

A mixed-use development requires a variance for reduced setbacks. The property is located within 500 feet of a hospital. What additional consideration must be addressed?

A LEED project requires tracking of regional materials. Materials are considered regional if they are extracted, harvested, or recovered, as well as manufactured within what distance of the project site?

An indemnification clause in a construction contract typically requires the contractor to:

A property owner wants to convert a single-family home into a duplex in an area zoned for single-family residential use. The conversion meets all building codes but violates density requirements. What approval is needed?

As-built drawings are typically required to be submitted:

AIA Document A401 is primarily used for:

A general contractor is building a 12,000 square foot commercial warehouse. The building permit fee is calculated at $8.50 per $1,000 of construction value. If the project value is $2,400,000, what is the building permit fee?

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your Florida General Contractor exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.