Your client requests a construction estimate for budget approval but design is only 30% complete. The architect indicates the building will be approximately 25,000 square feet. Which estimating approach provides the most appropriate level of accuracy?
Correct Answer
A) Square foot method with 20% contingency
At 30% design completion, the square foot method with higher contingency is most appropriate. Detailed takeoffs aren't possible with incomplete drawings, while the square foot method can provide reasonable budget estimates with adequate contingency for design development.
Why This Is the Correct Answer
At 30% design completion, detailed drawings and specifications are not available, making the square foot method the most practical approach. This method uses cost per square foot based on similar building types and can provide reasonable budget estimates even with limited design information. The 20% contingency appropriately accounts for the uncertainty inherent in early design phases and potential scope changes as the design develops.
Why the Other Options Are Wrong
Option C: Detailed quantity takeoff with 15% contingency
The assemblies method requires more detailed information about building systems and components than is typically available at 30% design completion. While more detailed than square foot pricing, it still needs substantial design development to be accurate.
Option D: Unit price method with 25% contingency
The unit price method requires detailed quantities of specific work items to be known, which are not available at 30% design completion. Additionally, 25% contingency is excessive and may lead to unrealistic budget expectations.
Memory Technique
Think '30% = 3 words = Square Foot Method' - the simpler the design info, the simpler the estimating method should be
Reference Hint
Look up estimating methods and design phases in construction management or cost estimating chapters of your reference materials
More Contract Admin Questions
A project experiences a 30-day delay due to unusually severe weather. The contract includes a liquidated damages clause of $1,000 per day for delays. If the weather delay is excusable but not compensable, what liquidated damages apply?
A commercial project requires a total of 12 inspections. The building department charges $85 per inspection for the first 5 inspections, $65 for inspections 6-10, and $45 for any additional inspections. What is the total inspection fee?
What document must be posted at the job site before a Certificate of Occupancy can be issued for a commercial building?
A mixed-use development requires a variance for reduced setbacks. The property is located within 500 feet of a hospital. What additional consideration must be addressed?
A LEED project requires tracking of regional materials. Materials are considered regional if they are extracted, harvested, or recovered, as well as manufactured within what distance of the project site?
An indemnification clause in a construction contract typically requires the contractor to:
A property owner wants to convert a single-family home into a duplex in an area zoned for single-family residential use. The conversion meets all building codes but violates density requirements. What approval is needed?
As-built drawings are typically required to be submitted:
AIA Document A401 is primarily used for:
A general contractor is building a 12,000 square foot commercial warehouse. The building permit fee is calculated at $8.50 per $1,000 of construction value. If the project value is $2,400,000, what is the building permit fee?
People Also Study
Business & Financial Management
120 questions Β· 70% to pass
Project Management
60 questions Β· 70% to pass
Related Study Resources
Previous Question
A project has a contract value of $850,000. The owner retains 10% on each payment application. If the contractor has submitted applications totaling $680,000, what is the total amount of retainage being held?
Next Question
What is the primary difference between a lump sum contract and a guaranteed maximum price (GMP) contract?
