EstatePass
Contract AdminContractsmedium40% of exam part

A contractor's cost-plus contract has a fee of 8% and actual project costs of $750,000. If there was a $50,000 cost overrun due to owner-requested changes, what is the contractor's total fee?

Correct Answer

D) $64,000

The contractor's fee is calculated on total allowable costs including approved changes. Total costs are $750,000 + $50,000 = $800,000. Fee = $800,000 × 0.08 = $64,000.

Answer Options
A
$60,000
B
$66,000
C
$68,000
D
$64,000

Why This Is the Correct Answer

In a cost-plus contract, the contractor's fee is calculated as a percentage of the total allowable project costs, which includes both the original costs and any approved change orders. Since the $50,000 cost overrun was due to owner-requested changes, it becomes part of the allowable costs. The total allowable costs are $750,000 + $50,000 = $800,000, and the contractor's fee is 8% of this total, which equals $64,000.

Why the Other Options Are Wrong

Option A: $60,000

This appears to add a flat amount to the base fee rather than calculating the percentage correctly on the total allowable costs.

Option C: $68,000

This calculates the fee only on the original project costs ($750,000 × 0.08 = $60,000) and incorrectly excludes the owner-requested changes from the fee calculation.

Memory Technique

Remember 'CAFE' - Cost-plus contracts include All Fees on Everything allowable (original costs + approved changes)

Reference Hint

Florida Building Construction Standards - Contract Types and Payment Methods chapter, specifically the section on Cost-Plus contracts and fee calculations

Was this explanation helpful?

More Contract Admin Questions

A project experiences a 30-day delay due to unusually severe weather. The contract includes a liquidated damages clause of $1,000 per day for delays. If the weather delay is excusable but not compensable, what liquidated damages apply?

A commercial project requires a total of 12 inspections. The building department charges $85 per inspection for the first 5 inspections, $65 for inspections 6-10, and $45 for any additional inspections. What is the total inspection fee?

What document must be posted at the job site before a Certificate of Occupancy can be issued for a commercial building?

A mixed-use development requires a variance for reduced setbacks. The property is located within 500 feet of a hospital. What additional consideration must be addressed?

A LEED project requires tracking of regional materials. Materials are considered regional if they are extracted, harvested, or recovered, as well as manufactured within what distance of the project site?

An indemnification clause in a construction contract typically requires the contractor to:

A property owner wants to convert a single-family home into a duplex in an area zoned for single-family residential use. The conversion meets all building codes but violates density requirements. What approval is needed?

As-built drawings are typically required to be submitted:

AIA Document A401 is primarily used for:

A general contractor is building a 12,000 square foot commercial warehouse. The building permit fee is calculated at $8.50 per $1,000 of construction value. If the project value is $2,400,000, what is the building permit fee?

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your Florida General Contractor exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.