EstatePass
Contract AdminProcedureshard13% of exam part

An activity has an Early Start of Day 10, Early Finish of Day 15, Late Start of Day 14, and Late Finish of Day 19. What is the total float for this activity?

Correct Answer

D) 4 days

Total float = Late Start - Early Start = 14 - 10 = 4 days. Alternatively, Total float = Late Finish - Early Finish = 19 - 15 = 4 days. Both calculations yield the same result.

Answer Options
A
9 days
B
6 days
C
2 days
D
4 days

Why This Is the Correct Answer

Total float represents the amount of time an activity can be delayed without affecting the project completion date. It is calculated using either Late Start minus Early Start or Late Finish minus Early Finish. Both formulas must yield the same result because the activity duration remains constant. In this case, both calculations (14-10 and 19-15) equal 4 days, confirming this is the correct total float.

Why the Other Options Are Wrong

Option A: 9 days

6 days is incorrect and doesn't correspond to any standard CPM calculation. This might result from adding values instead of subtracting or confusing different scheduling parameters.

Option B: 6 days

2 days is incorrect because it doesn't match either float calculation formula. This might result from confusing float with activity duration or making an arithmetic error.

Memory Technique

Remember 'LESE' - Late minus Early for Start or End gives you the same float. Both Late Start - Early Start and Late Finish - Early Finish must equal the same number.

Reference Hint

Look up Critical Path Method (CPM) scheduling in construction management chapters, specifically sections on float calculations and project scheduling terminology.

Was this explanation helpful?

More Contract Admin Questions

A project experiences a 30-day delay due to unusually severe weather. The contract includes a liquidated damages clause of $1,000 per day for delays. If the weather delay is excusable but not compensable, what liquidated damages apply?

A commercial project requires a total of 12 inspections. The building department charges $85 per inspection for the first 5 inspections, $65 for inspections 6-10, and $45 for any additional inspections. What is the total inspection fee?

What document must be posted at the job site before a Certificate of Occupancy can be issued for a commercial building?

A mixed-use development requires a variance for reduced setbacks. The property is located within 500 feet of a hospital. What additional consideration must be addressed?

A LEED project requires tracking of regional materials. Materials are considered regional if they are extracted, harvested, or recovered, as well as manufactured within what distance of the project site?

An indemnification clause in a construction contract typically requires the contractor to:

A property owner wants to convert a single-family home into a duplex in an area zoned for single-family residential use. The conversion meets all building codes but violates density requirements. What approval is needed?

As-built drawings are typically required to be submitted:

AIA Document A401 is primarily used for:

A general contractor is building a 12,000 square foot commercial warehouse. The building permit fee is calculated at $8.50 per $1,000 of construction value. If the project value is $2,400,000, what is the building permit fee?

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your Florida General Contractor exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.