Environmental impact assessment reveals endangered species habitat on a construction site covering 2.5 acres. The mitigation fee is $75,000 per acre, with a 15% administrative fee. What is the total environmental permit cost?

Correct Answer

C) $215,625

Base cost is 2.5 acres × $75,000 = $187,500. Adding 15% administrative fee: $187,500 × 1.15 = $215,625 total environmental permit cost.

Answer Options
A
$225,000
B
$258,750
C
$215,625
D
$187,500

Why This Is the Correct Answer

The correct answer is B because environmental permit costs require calculating both the base mitigation fee and administrative costs. First, multiply the site area (2.5 acres) by the per-acre fee ($75,000) to get $187,500. Then add the 15% administrative fee by multiplying $187,500 × 1.15 = $215,625. This represents the total environmental permit cost including all required fees.

Why the Other Options Are Wrong

Option A: $225,000

Option D incorrectly calculates the administrative fee, possibly using 38% instead of 15%, or making an error in the multiplication process.

Option B: $258,750

Option C appears to round up the base cost to $225,000 but fails to properly calculate or apply the 15% administrative fee to the correct base amount.

Option D: $187,500

Option A only calculates the base mitigation cost ($187,500) without including the required 15% administrative fee, making it incomplete.

Memory Technique

Remember 'BASE + ADMIN' - always calculate the base environmental cost first, then multiply by (1 + admin percentage) to get the total permit cost in one step.

Reference Hint

Florida Building Code Chapter 1, Environmental Regulations section, or local environmental permitting guidelines for fee structures and calculations

Was this explanation helpful?

More Contract Admin Questions

A project experiences a 30-day delay due to unusually severe weather. The contract includes a liquidated damages clause of $1,000 per day for delays. If the weather delay is excusable but not compensable, what liquidated damages apply?

A commercial project requires a total of 12 inspections. The building department charges $85 per inspection for the first 5 inspections, $65 for inspections 6-10, and $45 for any additional inspections. What is the total inspection fee?

What document must be posted at the job site before a Certificate of Occupancy can be issued for a commercial building?

A mixed-use development requires a variance for reduced setbacks. The property is located within 500 feet of a hospital. What additional consideration must be addressed?

A LEED project requires tracking of regional materials. Materials are considered regional if they are extracted, harvested, or recovered, as well as manufactured within what distance of the project site?

An indemnification clause in a construction contract typically requires the contractor to:

A property owner wants to convert a single-family home into a duplex in an area zoned for single-family residential use. The conversion meets all building codes but violates density requirements. What approval is needed?

As-built drawings are typically required to be submitted:

AIA Document A401 is primarily used for:

A general contractor is building a 12,000 square foot commercial warehouse. The building permit fee is calculated at $8.50 per $1,000 of construction value. If the project value is $2,400,000, what is the building permit fee?

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your Florida General Contractor exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.