EstatePass
Contract AdminPreconstructioneasy27% of exam part

A contractor estimates that 2,500 linear feet of electrical conduit installation will require 125 labor hours. What is the productivity rate in linear feet per hour?

Correct Answer

C) 20 linear feet per hour

Productivity rate = Total quantity ÷ Total hours = 2,500 linear feet ÷ 125 hours = 20 linear feet per hour. This rate can be used for estimating similar electrical conduit installation work on future projects.

Answer Options
A
30 linear feet per hour
B
15 linear feet per hour
C
20 linear feet per hour
D
25 linear feet per hour

Why This Is the Correct Answer

The productivity rate is calculated by dividing the total quantity of work by the total time required to complete it. In this case, 2,500 linear feet of conduit divided by 125 labor hours equals 20 linear feet per hour. This represents the rate at which workers can install electrical conduit under the given conditions. This metric is essential for accurate project scheduling and cost estimation in electrical work.

Why the Other Options Are Wrong

Option B: 15 linear feet per hour

This answer of 25 would result from dividing 125 into 2,500 incorrectly, possibly by miscalculating or confusing the order of operations in the productivity formula.

Option D: 25 linear feet per hour

This answer results from incorrectly calculating 2,500 ÷ 125 = 15, which is mathematically incorrect. The proper division yields 20, not 15.

Memory Technique

Remember 'QTT' - Quantity over Time equals Total productivity rate. Always put the work quantity on top and time on bottom when dividing.

Reference Hint

Look up productivity rates and labor estimating in construction management chapters, typically found in sections covering project scheduling and cost estimation.

Was this explanation helpful?

More Contract Admin Questions

A project experiences a 30-day delay due to unusually severe weather. The contract includes a liquidated damages clause of $1,000 per day for delays. If the weather delay is excusable but not compensable, what liquidated damages apply?

A commercial project requires a total of 12 inspections. The building department charges $85 per inspection for the first 5 inspections, $65 for inspections 6-10, and $45 for any additional inspections. What is the total inspection fee?

What document must be posted at the job site before a Certificate of Occupancy can be issued for a commercial building?

A mixed-use development requires a variance for reduced setbacks. The property is located within 500 feet of a hospital. What additional consideration must be addressed?

A LEED project requires tracking of regional materials. Materials are considered regional if they are extracted, harvested, or recovered, as well as manufactured within what distance of the project site?

An indemnification clause in a construction contract typically requires the contractor to:

A property owner wants to convert a single-family home into a duplex in an area zoned for single-family residential use. The conversion meets all building codes but violates density requirements. What approval is needed?

As-built drawings are typically required to be submitted:

AIA Document A401 is primarily used for:

A general contractor is building a 12,000 square foot commercial warehouse. The building permit fee is calculated at $8.50 per $1,000 of construction value. If the project value is $2,400,000, what is the building permit fee?

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your Florida General Contractor exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.