EstatePass
Contract AdminProcedureshard13% of exam part

According to Florida Building Code requirements, as-built drawings for commercial projects must be submitted to the building department within how many days of receiving the certificate of occupancy?

Correct Answer

B) 30 days

The Florida Building Code requires as-built drawings for commercial projects to be submitted to the building department within 30 days of receiving the certificate of occupancy to maintain accurate records.

Answer Options
A
90 days
B
30 days
C
As-built drawings are not required to be submitted
D
60 days

Why This Is the Correct Answer

The Florida Building Code specifically mandates that as-built drawings for commercial projects must be submitted within 30 days of receiving the certificate of occupancy. This requirement ensures that the building department maintains current and accurate records of the final construction details. The 30-day timeframe provides sufficient time for contractors to compile the necessary documentation while ensuring timely submission. This is a critical compliance requirement that contractors must meet to avoid potential penalties or issues with future permits.

Why the Other Options Are Wrong

Option A: 90 days

This is incorrect because as-built drawings are indeed required for commercial projects under the Florida Building Code. The submission of these drawings is mandatory, not optional, and serves important documentation and safety purposes.

Option C: As-built drawings are not required to be submitted

90 days is far too long according to Florida Building Code requirements. This extended timeframe would delay the building department's ability to maintain current records and could impact future inspections or modifications to the building.

Memory Technique

Think '30 days to document the commercial way' - commercial projects need as-built drawings submitted within 30 days of CO (Certificate of Occupancy)

Reference Hint

Florida Building Code, Chapter 1, Section 107 - Submittal Documents and Section 110 - Certificate of Occupancy requirements

Was this explanation helpful?

More Contract Admin Questions

A project experiences a 30-day delay due to unusually severe weather. The contract includes a liquidated damages clause of $1,000 per day for delays. If the weather delay is excusable but not compensable, what liquidated damages apply?

A commercial project requires a total of 12 inspections. The building department charges $85 per inspection for the first 5 inspections, $65 for inspections 6-10, and $45 for any additional inspections. What is the total inspection fee?

What document must be posted at the job site before a Certificate of Occupancy can be issued for a commercial building?

A mixed-use development requires a variance for reduced setbacks. The property is located within 500 feet of a hospital. What additional consideration must be addressed?

A LEED project requires tracking of regional materials. Materials are considered regional if they are extracted, harvested, or recovered, as well as manufactured within what distance of the project site?

An indemnification clause in a construction contract typically requires the contractor to:

A property owner wants to convert a single-family home into a duplex in an area zoned for single-family residential use. The conversion meets all building codes but violates density requirements. What approval is needed?

As-built drawings are typically required to be submitted:

AIA Document A401 is primarily used for:

A general contractor is building a 12,000 square foot commercial warehouse. The building permit fee is calculated at $8.50 per $1,000 of construction value. If the project value is $2,400,000, what is the building permit fee?

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your Florida General Contractor exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.