What is the maximum amount of retainage that can be withheld on Florida public projects once the project reaches 50% completion?
Correct Answer
A) 2.5%
Florida Statute 218.735 allows public entities to reduce retainage to 2.5% once a project reaches 50% completion, provided the contractor is performing satisfactorily and on schedule. This provides an incentive for good performance.
Why This Is the Correct Answer
Florida Statute 218.735 specifically allows public entities to reduce retainage from the standard 5% down to 2.5% once a construction project reaches 50% completion. This reduction is contingent upon the contractor demonstrating satisfactory performance and maintaining the project schedule. The statute was designed to improve contractor cash flow and provide an incentive for good performance on public projects. This 2.5% maximum retainage amount remains in effect for the remainder of the project duration.
Why the Other Options Are Wrong
Option B: 7.5%
7.5% exceeds the maximum allowable retainage under Florida Statute 218.735 and would be an illegal amount to withhold on public projects at any stage of completion.
Option C: 10%
5% is the standard retainage amount that can be withheld during the first 50% of project completion, but once the project reaches 50% completion with satisfactory performance, the retainage must be reduced to 2.5%.
Memory Technique
Think 'Half and Half-again': 50% completion triggers retainage reduction to half of the standard 5%, which equals 2.5%.
Reference Hint
Florida Statutes Chapter 218.735 - Retainage on public construction projects
More Contract Admin Questions
A project experiences a 30-day delay due to unusually severe weather. The contract includes a liquidated damages clause of $1,000 per day for delays. If the weather delay is excusable but not compensable, what liquidated damages apply?
A commercial project requires a total of 12 inspections. The building department charges $85 per inspection for the first 5 inspections, $65 for inspections 6-10, and $45 for any additional inspections. What is the total inspection fee?
What document must be posted at the job site before a Certificate of Occupancy can be issued for a commercial building?
A mixed-use development requires a variance for reduced setbacks. The property is located within 500 feet of a hospital. What additional consideration must be addressed?
A LEED project requires tracking of regional materials. Materials are considered regional if they are extracted, harvested, or recovered, as well as manufactured within what distance of the project site?
An indemnification clause in a construction contract typically requires the contractor to:
A property owner wants to convert a single-family home into a duplex in an area zoned for single-family residential use. The conversion meets all building codes but violates density requirements. What approval is needed?
As-built drawings are typically required to be submitted:
AIA Document A401 is primarily used for:
A general contractor is building a 12,000 square foot commercial warehouse. The building permit fee is calculated at $8.50 per $1,000 of construction value. If the project value is $2,400,000, what is the building permit fee?
People Also Study
Business & Financial Management
120 questions Β· 70% to pass
Project Management
60 questions Β· 70% to pass
Related Study Resources
Previous Question
According to Florida Building Code requirements, as-built drawings for commercial projects must be submitted to the building department within how many days of receiving the certificate of occupancy?
Next Question
What is the primary purpose of a performance bond in construction contracts?