What is the maximum down payment a contractor can legally collect under a home improvement contract governed by B&P Code 7159?

Correct Answer

C) $1,000 or 10% of the contract price, whichever is less

B&P 7159 limits down payments to $1,000 or 10% of the contract price, whichever is less.

Answer Options
A
$500 or 10% of the contract price, whichever is less
B
$1,500 or 15% of the contract price, whichever is less
C
$1,000 or 10% of the contract price, whichever is less
D
$2,000 or 20% of the contract price, whichever is less

Why This Is the Correct Answer

Business & Professions Code Section 7159 explicitly caps down payments on home improvement contracts at $1,000 or 10% of the contract price, whichever is less. This consumer protection provision prevents contractors from collecting large upfront sums before work begins.

Why the Other Options Are Wrong

Option A: $500 or 10% of the contract price, whichever is less

Option A has the percentage right (10%) but the dollar cap wrong ($500 instead of $1,000). The statutory cap is $1,000, not $500.

Option B: $1,500 or 15% of the contract price, whichever is less

Option B doubles both the correct figures β€” $1,500 instead of $1,000 and 15% instead of 10%. Neither figure matches the statute.

Option D: $2,000 or 20% of the contract price, whichever is less

Option D doubles the correct figures even further β€” $2,000 instead of $1,000 and 20% instead of 10%. This would allow far more upfront collection than the law permits.

Memory Technique

B&P 7159 = '$1,000 or 10%' β€” remember '1-10': one thousand dollars, ten percent. The '1' in $1,000 and the '10' go together. Always take whichever is LESS to protect the homeowner.

Was this explanation helpful?

More California Questions

A homeowner signs a $15,000 home improvement contract on Monday at 2 PM at the contractor's office. Under California law, what is the latest time the homeowner can cancel the contract without penalty?

A swimming pool contract for $28,000 is signed on Wednesday at the customer's home. The contract includes proper cancellation notices. If the customer wants to cancel, they must do so by when?

Under California's prompt payment law, if a contractor submits a proper payment request to a property owner, payment is due within how many days?

A general contractor hires a subcontractor for $22,000. The general contractor receives payment from the owner but fails to pay the subcontractor within how many days, subjecting themselves to penalty interest?

Under California Civil Code Section 8180, when must a subcontractor serve a preliminary notice on a private work project?

Which of the following contracts is NOT subject to the 3-day right to cancel under California law?

A subcontractor completes roofing work on Tuesday, March 15th. The general contractor is paid by the owner on Friday, March 25th. Under California prompt payment laws, what is the latest date the general contractor must pay the subcontractor?

A contractor receives a progress payment of $18,000 from a property owner on Monday. The contractor owes subcontractors $12,000 of this amount. By what day must the contractor pay the subcontractors?

A swimming pool contractor enters into a $45,000 contract to install an in-ground pool. The contract includes a $5,000 down payment. What is the maximum down payment the contractor can legally collect under California law?

A contractor completes $15,000 worth of electrical work on a commercial building. The property owner disputes $3,000 of the charges. Under California prompt payment law, what amount must the owner pay within the required timeframe to avoid penalties?

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your contractor license exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.