Under Virginia environmental regulations, what is required before disturbing more than 2,500 square feet of land on a construction project?
Correct Answer
B) Erosion and sediment control plan
Virginia law requires an erosion and sediment control plan for land disturbing activities of 2,500 square feet or more to prevent soil erosion and protect water quality.
Why This Is the Correct Answer
Virginia's Erosion and Sediment Control Law requires that any land-disturbing activity of 2,500 square feet or more must have an approved erosion and sediment control plan in place before disturbance begins. This plan must be submitted to the local program authority and approved prior to land disturbance to protect water quality.
Why the Other Options Are Wrong
Option A: Groundwater monitoring plan
A groundwater monitoring plan is not required by Virginia's erosion and sediment control regulations for typical construction projects. Groundwater monitoring is associated with remediation sites or facilities with underground storage tanks, not standard construction land disturbance.
Option C: Wetlands delineation study
A wetlands delineation study is required when construction may impact wetland areas regulated under Section 404 of the Clean Water Act or the Virginia Water Protection Permit program β not as a general requirement for any 2,500 sq ft disturbance.
Option D: Environmental impact assessment
A full environmental impact assessment (EIA) is associated with major federal or state projects under NEPA or SEPA processes. It is not the standard requirement triggered by the 2,500 sq ft threshold under Virginia's erosion and sediment control regulations.
Memory Technique
2,500 square feet is roughly the size of a modest house footprint. Picture mud and sediment washing off a house-sized patch of bare dirt into a stream β that visual explains why Virginia requires a plan at exactly this scale.
More Virginia Questions
Under Virginia law (Title 54.1), what is the minimum net worth requirement for a Class A contractor license?
A Virginia contractor fails to pay a subcontractor $18,500 for completed work. Under Virginia mechanics lien law, within how many days must the subcontractor file a memorandum of lien to preserve their lien rights?
A Virginia contractor employs 8 workers with a total annual payroll of $420,000. Using the standard construction rate of $8.50 per $100 of payroll, what is the annual workers' compensation premium?
A Virginia contractor fails to pay subcontractors on a $180,000 project. Under Virginia mechanics lien law, what is the maximum time period a subcontractor has to file a mechanics lien after last furnishing labor or materials?
Under Virginia contractor law, what happens to a contractor's license if they fail to maintain required insurance coverage?
A contractor fails to pay a subcontractor and the subcontractor files a mechanics lien. Under Virginia law, within how many days must the general contractor post a bond to release the lien from the property?
A Class B contractor in Virginia completed $850,000 worth of work in the current license period and has contracts totaling $1,200,000 for the next period. What action must the contractor take?
A homeowner hired an unlicensed contractor for a $45,000 kitchen renovation. Under Virginia law, what remedy is available to the homeowner?
Calculate the required bond amount for a Virginia Class A contractor with average annual gross receipts of $2,800,000 over the past three years.
A Class C contractor in Virginia wants to install a residential HVAC system valued at $12,000. The contractor's specialty classification is electrical work. What must the contractor do to legally perform this work?
People Also Study
Business & Financial Management
120 questions Β· 70% to pass
Contract Administration
60 questions Β· 70% to pass
Project Management
60 questions Β· 70% to pass
Related Study Resources
Previous Question
Calculate the mechanics lien amount a Virginia supplier can claim: Materials delivered worth $28,000, labor provided worth $12,000, equipment rental worth $8,000. What is the maximum lien amount?
Next Question
A Virginia Class A contractor wants to add electrical work to their license classification. What must they demonstrate to the Board?