EstatePass
VirginiaVA Supplementeasy100% of exam part

Calculate the mechanics lien amount a Virginia supplier can claim: Materials delivered worth $28,000, labor provided worth $12,000, equipment rental worth $8,000. What is the maximum lien amount?

Correct Answer

D) $48,000

Virginia mechanics lien law allows liens for the total amount of materials, labor, and equipment provided: $28,000 + $12,000 + $8,000 = $48,000.

Answer Options
A
$28,000
B
$35,000
C
$40,000
D
$48,000

Why This Is the Correct Answer

Virginia mechanics lien law allows a lien claimant to include all compensable items: materials ($28,000) + labor ($12,000) + equipment rental ($8,000) = $48,000. All three categories are lienable under Virginia Code, so the maximum valid lien amount is the full sum.

Why the Other Options Are Wrong

Option A: $28,000

$28,000 represents only the materials portion. This answer incorrectly excludes labor and equipment rental, both of which are lienable items under Virginia law.

Option B: $35,000

$35,000 equals materials plus labor ($28,000 + $12,000) but omits the $8,000 equipment rental. Equipment rental is a lienable item in Virginia and must be included in the total.

Option C: $40,000

$40,000 equals materials plus equipment ($28,000 + $8,000) but omits the $12,000 labor, or it could represent other partial combinations. Either way, all three items must be summed for the correct answer.

Memory Technique

Virginia lien = M + L + E: Materials + Labor + Equipment. Add all three: $28K + $12K + $8K = $48K. The mnemonic 'MLE = $48K' covers the full picture.

Was this explanation helpful?

More Virginia Questions

Under Virginia law (Title 54.1), what is the minimum net worth requirement for a Class A contractor license?

A Virginia contractor fails to pay a subcontractor $18,500 for completed work. Under Virginia mechanics lien law, within how many days must the subcontractor file a memorandum of lien to preserve their lien rights?

A Virginia contractor employs 8 workers with a total annual payroll of $420,000. Using the standard construction rate of $8.50 per $100 of payroll, what is the annual workers' compensation premium?

A Virginia contractor fails to pay subcontractors on a $180,000 project. Under Virginia mechanics lien law, what is the maximum time period a subcontractor has to file a mechanics lien after last furnishing labor or materials?

Under Virginia contractor law, what happens to a contractor's license if they fail to maintain required insurance coverage?

A contractor fails to pay a subcontractor and the subcontractor files a mechanics lien. Under Virginia law, within how many days must the general contractor post a bond to release the lien from the property?

A Class B contractor in Virginia completed $850,000 worth of work in the current license period and has contracts totaling $1,200,000 for the next period. What action must the contractor take?

A homeowner hired an unlicensed contractor for a $45,000 kitchen renovation. Under Virginia law, what remedy is available to the homeowner?

Calculate the required bond amount for a Virginia Class A contractor with average annual gross receipts of $2,800,000 over the past three years.

A Class C contractor in Virginia wants to install a residential HVAC system valued at $12,000. The contractor's specialty classification is electrical work. What must the contractor do to legally perform this work?

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your contractor license exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.