A Virginia contractor fails to pay subcontractors on a $180,000 project. Under Virginia mechanics lien law, what is the maximum time period a subcontractor has to file a mechanics lien after last furnishing labor or materials?
Correct Answer
C) 90 days
Virginia mechanics lien law requires that a mechanics lien be filed within 90 days after last furnishing labor or materials to the project.
Why This Is the Correct Answer
Under Virginia Code § 43-4, subcontractors must file a mechanics lien within 90 days after they last furnished labor, materials, or services to the project. This 90-day deadline is strictly enforced and begins running from the final date of work performed or materials delivered by the specific subcontractor, not from project completion. The statute provides this timeframe to balance the rights of unpaid subcontractors with property owners' need for certainty regarding potential liens.
Why the Other Options Are Wrong
Option A: 150 days
150 days exceeds Virginia's statutory requirement. This extended timeframe might be confused with other states' lien laws or different types of construction-related deadlines, but Virginia specifically mandates the shorter 90-day period for mechanics liens.
Option B: 60 days
60 days is too short under Virginia law. While some preliminary notice requirements or other construction-related deadlines may use shorter periods, the mechanics lien filing deadline specifically allows subcontractors 90 days to protect their lien rights.
Option D: 120 days
120 days exceeds Virginia's statutory deadline. This timeframe might be associated with other states' mechanics lien laws or different types of legal deadlines, but Virginia Code clearly establishes 90 days as the maximum period for filing mechanics liens.
Memory Technique
Remember 'Virginia 90' - like a right angle (90 degrees), Virginia gives subcontractors exactly 90 days to file their mechanics lien after last furnishing work.
More va-supplement Questions
Under Virginia law (Title 54.1), what is the minimum net worth requirement for a Class A contractor license?
A Virginia contractor fails to pay a subcontractor $18,500 for completed work. Under Virginia mechanics lien law, within how many days must the subcontractor file a memorandum of lien to preserve their lien rights?
A Virginia contractor employs 8 workers with a total annual payroll of $420,000. Using the standard construction rate of $8.50 per $100 of payroll, what is the annual workers' compensation premium?
Under Virginia contractor law, what happens to a contractor's license if they fail to maintain required insurance coverage?
A contractor fails to pay a subcontractor and the subcontractor files a mechanics lien. Under Virginia law, within how many days must the general contractor post a bond to release the lien from the property?
A Class B contractor in Virginia completed $850,000 worth of work in the current license period and has contracts totaling $1,200,000 for the next period. What action must the contractor take?
A homeowner hired an unlicensed contractor for a $45,000 kitchen renovation. Under Virginia law, what remedy is available to the homeowner?
Calculate the required bond amount for a Virginia Class A contractor with average annual gross receipts of $2,800,000 over the past three years.
A Class C contractor in Virginia wants to install a residential HVAC system valued at $12,000. The contractor's specialty classification is electrical work. What must the contractor do to legally perform this work?
A Virginia contractor discovers an underground storage tank during excavation. The tank appears to be leaking petroleum products. What is the required notification timeframe to Virginia DEQ?
People Also Study
Business & Financial Management
120 questions · 70% to pass
Contract Administration
60 questions · 70% to pass
Project Management
60 questions · 70% to pass
Related Study Resources
Previous Question
Calculate Virginia workers compensation premium: Payroll of $485,000, rate of $12.50 per $100 of payroll. What is the annual premium?
Next Question
A Virginia contractor completes a $125,000 commercial project. The owner disputes $18,000 in charges. What is the maximum mechanics lien amount the contractor can file under Virginia law?
