EstatePass
va-supplementVirginia State Supplementmedium

A Virginia contractor fails to pay a subcontractor $18,500 for completed work. Under Virginia mechanics lien law, within how many days must the subcontractor file a memorandum of lien to preserve their lien rights?

Correct Answer

A) 90 days from last day of work

Virginia Code § 43-4 requires subcontractors to file a memorandum of lien within 90 days from the last day work was performed to preserve lien rights.

Answer Options
A
90 days from last day of work
B
120 days from last day of work
C
60 days from last day of work
D
30 days from last day of work

Why This Is the Correct Answer

Under Virginia Code § 43-4, subcontractors must file a memorandum of lien within 90 days from the last day work was performed to preserve their lien rights. This 90-day deadline is specifically established for subcontractors and is a critical requirement to maintain the validity of their mechanics lien claim against the property for unpaid work.

Why the Other Options Are Wrong

Option B: 120 days from last day of work

120 days exceeds Virginia's statutory requirement. While this might seem like a reasonable timeframe, Virginia law specifically sets the deadline at 90 days, not 120 days. Using this longer timeframe would result in the subcontractor losing their lien rights entirely.

Option C: 60 days from last day of work

60 days is too short under Virginia law. While this timeframe might apply in some other states or for different types of claims, Virginia specifically requires 90 days for subcontractors to file their memorandum of lien from the last day of work performed.

Option D: 30 days from last day of work

30 days is far too short and would not provide adequate time for subcontractors to preserve their lien rights. Virginia recognizes that subcontractors need more time than this brief period to file the necessary paperwork and establish their lien claims properly.

Memory Technique

Remember 'Virginia 90' - Virginia gives subcontractors a full 90 days (3 months) to file their lien, which is more generous than the typical 30-60 day periods in many other states.

Was this explanation helpful?

More va-supplement Questions

Under Virginia law (Title 54.1), what is the minimum net worth requirement for a Class A contractor license?

A Virginia contractor employs 8 workers with a total annual payroll of $420,000. Using the standard construction rate of $8.50 per $100 of payroll, what is the annual workers' compensation premium?

A Virginia contractor fails to pay subcontractors on a $180,000 project. Under Virginia mechanics lien law, what is the maximum time period a subcontractor has to file a mechanics lien after last furnishing labor or materials?

Under Virginia contractor law, what happens to a contractor's license if they fail to maintain required insurance coverage?

A contractor fails to pay a subcontractor and the subcontractor files a mechanics lien. Under Virginia law, within how many days must the general contractor post a bond to release the lien from the property?

A Class B contractor in Virginia completed $850,000 worth of work in the current license period and has contracts totaling $1,200,000 for the next period. What action must the contractor take?

A homeowner hired an unlicensed contractor for a $45,000 kitchen renovation. Under Virginia law, what remedy is available to the homeowner?

Calculate the required bond amount for a Virginia Class A contractor with average annual gross receipts of $2,800,000 over the past three years.

A Class C contractor in Virginia wants to install a residential HVAC system valued at $12,000. The contractor's specialty classification is electrical work. What must the contractor do to legally perform this work?

A Virginia contractor discovers an underground storage tank during excavation. The tank appears to be leaking petroleum products. What is the required notification timeframe to Virginia DEQ?

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your Florida General Contractor exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.