Under ORS 87, a material supplier delivers lumber on March 15th and their final delivery is April 10th. They are not paid. What is the deadline to file their construction lien?

Correct Answer

D) July 9th

Material suppliers have 75 days from their last delivery to file a lien. 75 days from April 10th is July 9th (April has 30 days, so 20 days in April + 31 days in May + 31 days in June + 9 days in July = 91 total days, but counting from April 10th: 75 days later is July 9th).

Answer Options
A
May 30th
B
June 24th
C
August 8th
D
July 9th

Why This Is the Correct Answer

Material suppliers have 75 days from their last delivery to file a lien. 75 days from April 10th is July 9th (April has 30 days, so 20 days in April + 31 days in May + 31 days in June + 9 days in July = 91 total days, but counting from April 10th: 75 days later is July 9th).

Was this explanation helpful?

More or-supplement Questions

Under ORS 701, what is the minimum amount of public liability insurance required for a CCB licensed contractor?

An employee is injured on a job site. The contractor's workers compensation premium was $2,400 annually. If they were operating without coverage, what is the minimum penalty multiplier applied to the premium?

A contractor completes a $12,000 deck project but the homeowner claims defective work. Under ORS 87, how long does the contractor have to file a lien for unpaid amounts?

Under ORS 701, what is the maximum amount a residential contractor can collect as a down payment before starting work?

A homeowner cancels a $8,000 roofing contract within the 3-day right to cancel period. The contractor had already ordered $1,200 in custom materials. How much can the contractor retain?

A general contractor hires a subcontractor who performs $15,000 worth of electrical work. The property owner pays the general contractor but the general contractor fails to pay the subcontractor. Calculate the subcontractor's maximum lien claim under ORS 87.

A renovation project in a 1972 home will disturb 15 square feet of painted trim. The contractor is not RRP certified. What must they do under Oregon lead regulations?

What is the minimum experience requirement for obtaining an Oregon CCB contractor license?

A homeowner hired an unlicensed contractor who abandoned a $25,000 project. The homeowner wants to file a claim with the CCB. What is the likely outcome?

A residential contractor completes a $35,000 kitchen remodel but fails to obtain required permits. Under Oregon law, what is the potential penalty?

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your Florida General Contractor exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.