Under Louisiana's Private Works Act, what is the maximum time period after substantial completion that a contractor has to file a lien claim on private property?

Correct Answer

C) 60 days

Louisiana's Private Works Act allows contractors 60 days from substantial completion to file a lien claim on private property.

Answer Options
A
30 days
B
120 days
C
60 days
D
90 days

Why This Is the Correct Answer

Louisiana's Private Works Act establishes a 60-day window from substantial completion for contractors (and subcontractors, suppliers, and laborers) to file a statement of claim and privilege (lien) against private property. This 60-day period is the primary deadline and is one of the most tested provisions on the Louisiana contractor exam.

Why the Other Options Are Wrong

Option A: 30 days

30 days is shorter than the Louisiana statutory period and is associated with lien deadlines in other states (e.g., Texas for some notice requirements). Louisiana provides the longer 60-day window.

Option B: 120 days

120 days is more than double the actual period. While some other states have longer lien windows (e.g., certain commercial project rules), Louisiana's Private Works Act uses 60 days, not 120.

Option D: 90 days

90 days appears in federal Miller Act bond claims for public projects and some states' private lien laws, but Louisiana's Private Works Act sets 60 days for private property lien claims.

Memory Technique

Louisiana = Lien in 60. Think of a 60-second minute — in Louisiana, you get '60' to file your lien. Alternatively: Louisiana has 6 letters in 'lien' — no wait, that's 4. Better: Louisiana 60 days = 2 months. File by the 2-month mark after substantial completion.

Was this explanation helpful?

More Louisiana Questions

A contractor in Louisiana completes $85,000 worth of work on a residential project. The owner pays $70,000 but disputes the remaining $15,000. If the contractor files a lien claim, what percentage penalty can be awarded if the contractor prevails in court?

A contractor discovers contaminated soil during excavation that requires special disposal. The disposal cost is $12,000, and transportation is $3,500. If this was not foreseeable from the contract documents, who typically bears this cost under Louisiana law?

A construction worker is injured on a Louisiana job site. The contractor's workers' compensation carrier has 15 days to investigate. If they don't respond within this period, what happens to the claim?

Under Louisiana law, what is the minimum amount of workers' compensation insurance coverage required for construction contractors?

A contractor's employee is injured on a job site in Louisiana. The contractor has workers' compensation insurance. Which statement is correct regarding the employee's rights?

Under Louisiana Civil Code, if a building contract does not specify a completion date, when is the work considered to be due?

Under Louisiana building codes, what is the minimum width required for emergency egress windows in bedrooms?

A Class B contractor in Louisiana wants to bid on a project worth $175,000. What action must they take?

A contractor's worker is injured and files for workers' compensation. The injury occurred due to the worker's intoxication. Under Louisiana law, what is the likely outcome?

A general contractor discovers contaminated soil during excavation for a commercial project in Louisiana. Which state agency must be notified?

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your contractor license exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.