In Louisiana, what is the statute of limitations for filing a lawsuit based on construction defects in residential buildings?
Correct Answer
D) 5 years from completion
Louisiana Civil Code provides a 5-year statute of limitations for construction defect claims in residential buildings, running from completion of the work.
Why This Is the Correct Answer
Louisiana Civil Code provides a 5-year peremptive period for claims arising from construction defects in residential buildings, running from the date of completion of the work. This is separate from the 10-year period for immovable property under Article 2324.
Why the Other Options Are Wrong
Option A: 2 years from completion
2 years is not the correct limitations period for construction defects in Louisiana. This timeframe applies to personal injury or other tort claims, not residential construction defect claims.
Option B: 10 years from completion
10 years applies under Louisiana Civil Code Article 2324 to actions against contractors for defects in immovable property (commercial/structural), not specifically to residential building defect claims.
Option C: 1 year from discovery
1 year from discovery is a common discovery rule used in many states and tort contexts, but Louisiana's residential construction defect period runs from completion, not from when defects are found.
Memory Technique
Remember: '5 for a house, 10 for the land.' Residential construction defects = 5 years; structural/immovable property defects under Article 2324 = 10 years. A house sits on land, but the two rules are different.
More Louisiana Questions
A contractor in Louisiana completes $85,000 worth of work on a residential project. The owner pays $70,000 but disputes the remaining $15,000. If the contractor files a lien claim, what percentage penalty can be awarded if the contractor prevails in court?
A contractor discovers contaminated soil during excavation that requires special disposal. The disposal cost is $12,000, and transportation is $3,500. If this was not foreseeable from the contract documents, who typically bears this cost under Louisiana law?
A construction worker is injured on a Louisiana job site. The contractor's workers' compensation carrier has 15 days to investigate. If they don't respond within this period, what happens to the claim?
Under Louisiana law, what is the minimum amount of workers' compensation insurance coverage required for construction contractors?
A contractor's employee is injured on a job site in Louisiana. The contractor has workers' compensation insurance. Which statement is correct regarding the employee's rights?
Under Louisiana Civil Code, if a building contract does not specify a completion date, when is the work considered to be due?
Under Louisiana building codes, what is the minimum width required for emergency egress windows in bedrooms?
A Class B contractor in Louisiana wants to bid on a project worth $175,000. What action must they take?
A contractor's worker is injured and files for workers' compensation. The injury occurred due to the worker's intoxication. Under Louisiana law, what is the likely outcome?
A general contractor discovers contaminated soil during excavation for a commercial project in Louisiana. Which state agency must be notified?
People Also Study
Business & Financial Management
120 questions Β· 70% to pass
Contract Administration
60 questions Β· 70% to pass
Project Management
60 questions Β· 70% to pass
Related Study Resources
Previous Question
Under Louisiana's Private Works Act, what is the maximum time period after substantial completion that a contractor has to file a lien claim on private property?
Next Question
A contractor is renovating a building built in 1968 in Louisiana. What lead-safe work practice certification is required?