EstatePass
CaliforniaContractseasy20% of exam part

Under B&P Code 7159, which of the following information is NOT required to be included in a home improvement contract?

Correct Answer

D) The homeowner's credit score

The homeowner's credit score is not required information in a home improvement contract under B&P Code 7159.

Answer Options
A
The contractor's license number
B
A description of the work to be performed
C
The total price of the contract
D
The homeowner's credit score

Why This Is the Correct Answer

The homeowner's credit score is purely financial/personal information held by the homeowner and has no bearing on the scope, price, or terms of the work. B&P Code 7159 focuses on disclosures that protect the homeowner regarding the work itself — not the homeowner's personal financial profile.

Why the Other Options Are Wrong

Option A: The contractor's license number

The contractor's license number is explicitly required under B&P Code 7159 so homeowners can verify the contractor is properly licensed with the CSLB. Omitting it is a statutory violation.

Option B: A description of the work to be performed

A description of the work to be performed is a core requirement. Without it, the contract lacks specificity and the homeowner has no clear basis to hold the contractor accountable to a defined scope.

Option C: The total price of the contract

The total price (or method of calculating price) is a mandatory disclosure. Homeowners must know their total financial obligation before signing.

Memory Technique

Think of B&P 7159 as covering the '3 Ws of the job': Who (license number), What (work description), and How Much (price). A credit score is about the homeowner's wallet, not the job — it doesn't belong.

Was this explanation helpful?

More California Questions

A homeowner signs a $15,000 home improvement contract on Monday at 2 PM at the contractor's office. Under California law, what is the latest time the homeowner can cancel the contract without penalty?

A swimming pool contract for $28,000 is signed on Wednesday at the customer's home. The contract includes proper cancellation notices. If the customer wants to cancel, they must do so by when?

Under California's prompt payment law, if a contractor submits a proper payment request to a property owner, payment is due within how many days?

A general contractor hires a subcontractor for $22,000. The general contractor receives payment from the owner but fails to pay the subcontractor within how many days, subjecting themselves to penalty interest?

Under California Civil Code Section 8180, when must a subcontractor serve a preliminary notice on a private work project?

Which of the following contracts is NOT subject to the 3-day right to cancel under California law?

A subcontractor completes roofing work on Tuesday, March 15th. The general contractor is paid by the owner on Friday, March 25th. Under California prompt payment laws, what is the latest date the general contractor must pay the subcontractor?

A contractor receives a progress payment of $18,000 from a property owner on Monday. The contractor owes subcontractors $12,000 of this amount. By what day must the contractor pay the subcontractors?

A swimming pool contractor enters into a $45,000 contract to install an in-ground pool. The contract includes a $5,000 down payment. What is the maximum down payment the contractor can legally collect under California law?

A contractor completes $15,000 worth of electrical work on a commercial building. The property owner disputes $3,000 of the charges. Under California prompt payment law, what amount must the owner pay within the required timeframe to avoid penalties?

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your contractor license exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.