During a framing inspection, you discover that 2x6 wall studs are spaced 24 inches on center instead of the planned 16 inches. The wall will support a second floor. What is the most appropriate action according to Michigan Building Code?
Correct Answer
C) Reframe the wall with studs at 16" on center as originally planned
Load-bearing walls supporting a second floor typically require 16" stud spacing. The safest approach is to reframe according to the approved plans.
Why This Is the Correct Answer
Load-bearing walls supporting a second floor typically require 16" stud spacing. The safest approach is to reframe according to the approved plans.
More mi-builder Questions
A residential foundation wall in Michigan is 8 feet high with 2 feet above grade. The backfill exerts lateral pressure of 30 psf per foot of depth. What is the maximum lateral pressure at the bottom of the foundation wall?
A builder discovers that the electrical service entrance was installed without proper permits. According to Michigan law, what is the most appropriate next step?
What is the maximum allowable span for a 2x8 floor joist (Grade 2 Douglas Fir) at 16" O.C. with 40 psf live load and 10 psf dead load according to Michigan Building Code span tables?
According to Michigan Building Code, what is the maximum height of a wood-framed bearing wall using 2x4 studs with standard construction?
A homeowner requests to convert a bedroom into a bathroom on the second floor. What is the primary Michigan code concern the builder must address?
According to Michigan plumbing regulations, what is the minimum pipe size required for a water service line serving a single-family residence?
A contractor is building a basement foundation wall that is 8 feet high and will retain 6 feet of soil. What is the minimum wall thickness required by the Michigan Building Code for poured concrete?
A homeowner wants to install a gas fireplace in their living room. The contractor notices the existing gas line is 1/2 inch black iron pipe. For a 40,000 BTU fireplace with a 25-foot run, is this pipe size adequate according to Michigan gas code?
During a framing inspection, the building official notes that the contractor used 2x4 studs at 24 inches on center for an exterior wall. According to Michigan Building Code, what is the maximum wall height allowed for this configuration?
A contractor is installing a beam to support floor joists. The beam must carry a total load of 8,000 pounds over a 12-foot span. If the allowable fiber stress for the lumber grade is 1,200 psi, what is the minimum required section modulus?
People Also Study
Business & Financial Management
120 questions Β· 70% to pass
Contract Administration
60 questions Β· 70% to pass
Project Management
60 questions Β· 70% to pass
Related Study Resources
Previous Question
You are installing windows in a new home in Climate Zone 6A. The total window area is 320 square feet, and the gross wall area is 1,600 square feet. Calculate the window-to-wall ratio and determine if it meets Michigan Energy Code requirements without additional compliance paths.
Next Question
A contractor discovers that the electrical service entrance was installed without proper permits during a residential renovation. According to Michigan law, what is the most appropriate course of action?