During a framing inspection, you discover that 2x6 wall studs are spaced 24 inches on center instead of the planned 16 inches. The wall will support a second floor. What is the most appropriate action according to Michigan Building Code?

Correct Answer

C) Reframe the wall with studs at 16" on center as originally planned

Load-bearing walls supporting a second floor typically require 16" stud spacing. The safest approach is to reframe according to the approved plans.

Answer Options
A
Add blocking between studs to reduce the effective spacing
B
Proceed as planned since 2x6 studs can handle the load at 24" spacing
C
Reframe the wall with studs at 16" on center as originally planned
D
Upgrade to 2x8 studs and maintain 24" spacing

Why This Is the Correct Answer

Option C (Reframe the wall with studs at 16" on center as originally planned) is correct. Load-bearing walls supporting a second floor require studs at 16" on center per the approved plans and code. The contractor must correct the work to conform to approved plans — simply adding blocking or upgrading to larger studs is not an approved substitution without engineering review.

Why the Other Options Are Wrong

Option A: Add blocking between studs to reduce the effective spacing

Option A (Add blocking between studs) is incorrect. Blocking between studs does not structurally substitute for proper stud spacing in a load-bearing wall. Blocking serves lateral bracing purposes, not vertical load transfer. This workaround does not bring the wall into compliance.

Option B: Proceed as planned since 2x6 studs can handle the load at 24" spacing

Option B (Proceed as planned since 2x6 studs can handle the load at 24") is incorrect. While 2x6 studs at 24" OC may work in some non-load-bearing applications, this assumes no engineering review was done for this change. Deviating from approved plans without authorization is a code violation.

Option D: Upgrade to 2x8 studs and maintain 24" spacing

Option D (Upgrade to 2x8 studs at 24" spacing) is incorrect. Substituting a larger member size is an engineering decision that requires a plan change approval and engineering justification — a contractor cannot unilaterally make this substitution. It also doesn't follow the approved plans.

Memory Technique

Remember: 'Fix it to fit the plan.' Approved plans are the law on the jobsite. When in doubt, revert to the approved design rather than improvising structural substitutions.

Was this explanation helpful?

More Michigan Questions

A residential foundation wall in Michigan is 8 feet high with 2 feet above grade. The backfill exerts lateral pressure of 30 psf per foot of depth. What is the maximum lateral pressure at the bottom of the foundation wall?

A builder discovers that the electrical service entrance was installed without proper permits. According to Michigan law, what is the most appropriate next step?

What is the maximum allowable span for a 2x8 floor joist (Grade 2 Douglas Fir) at 16" O.C. with 40 psf live load and 10 psf dead load according to Michigan Building Code span tables?

According to Michigan Building Code, what is the maximum height of a wood-framed bearing wall using 2x4 studs with standard construction?

A homeowner requests to convert a bedroom into a bathroom on the second floor. What is the primary Michigan code concern the builder must address?

According to Michigan plumbing regulations, what is the minimum pipe size required for a water service line serving a single-family residence?

A contractor is building a basement foundation wall that is 8 feet high and will retain 6 feet of soil. What is the minimum wall thickness required by the Michigan Building Code for poured concrete?

A homeowner wants to install a gas fireplace in their living room. The contractor notices the existing gas line is 1/2 inch black iron pipe. For a 40,000 BTU fireplace with a 25-foot run, is this pipe size adequate according to Michigan gas code?

During a framing inspection, the building official notes that the contractor used 2x4 studs at 24 inches on center for an exterior wall. According to Michigan Building Code, what is the maximum wall height allowed for this configuration?

A contractor is installing a beam to support floor joists. The beam must carry a total load of 8,000 pounds over a 12-foot span. If the allowable fiber stress for the lumber grade is 1,200 psi, what is the minimum required section modulus?

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your contractor license exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.