Calculate the maximum lien amount a material supplier can claim under Oregon law for materials delivered to a residential construction project with a total contract value of $85,000, where the supplier provided $15,000 in materials.
Correct Answer
D) $15,000
Material suppliers can lien for the actual value of materials provided, which is $15,000 in this case.
Why This Is the Correct Answer
Under Oregon lien law (ORS 87), a material supplier's lien claim is limited to the actual value of materials provided — not a percentage of the contract value. The supplier delivered $15,000 in materials, so the maximum lien is $15,000. Lien rights are tied to the actual contribution, not the overall contract size.
Why the Other Options Are Wrong
Option A: $21,250
$21,250 appears to be 25% of the $85,000 contract value. Oregon lien law does not base supplier lien amounts on a percentage of the total contract — it is based on the actual value of materials furnished.
Option B: $17,000
$17,000 appears to be 20% of the $85,000 contract value. Again, Oregon lien law does not use a percentage-of-contract calculation for material suppliers. The actual value of materials provided controls.
Option C: $25,500
$25,500 appears to be 30% of the $85,000 contract. Same error — lien amounts for suppliers are not derived from contract percentages.
Memory Technique
Supplier lien = what you gave. You gave $15,000 in materials, you can lien for $15,000. The contract total is a red herring.
More Oregon Questions
Under ORS 701, what is the minimum amount of public liability insurance required for a CCB licensed contractor?
An employee is injured on a job site. The contractor's workers compensation premium was $2,400 annually. If they were operating without coverage, what is the minimum penalty multiplier applied to the premium?
A contractor completes a $12,000 deck project but the homeowner claims defective work. Under ORS 87, how long does the contractor have to file a lien for unpaid amounts?
Under ORS 701, what is the maximum amount a residential contractor can collect as a down payment before starting work?
A homeowner cancels a $8,000 roofing contract within the 3-day right to cancel period. The contractor had already ordered $1,200 in custom materials. How much can the contractor retain?
A general contractor hires a subcontractor who performs $15,000 worth of electrical work. The property owner pays the general contractor but the general contractor fails to pay the subcontractor. Calculate the subcontractor's maximum lien claim under ORS 87.
A renovation project in a 1972 home will disturb 15 square feet of painted trim. The contractor is not RRP certified. What must they do under Oregon lead regulations?
What is the minimum experience requirement for obtaining an Oregon CCB contractor license?
A homeowner hired an unlicensed contractor who abandoned a $25,000 project. The homeowner wants to file a claim with the CCB. What is the likely outcome?
A residential contractor completes a $35,000 kitchen remodel but fails to obtain required permits. Under Oregon law, what is the potential penalty?