CaliforniaContractsmedium20% of exam part

Calculate the maximum down payment a contractor can legally request for a $24,000 kitchen remodel under B&P Code 7159.

Correct Answer

D) $1,000

B&P 7159 limits down payments to the lesser of $1,000 or 10% of contract price. 10% of $24,000 = $2,400, but the maximum is capped at $1,000.

Answer Options
A
$2,400
B
$7,200
C
$4,800
D
$1,000

Why This Is the Correct Answer

B&P Code Section 7159 limits the down payment to the lesser of 10% of the total contract price OR $1,000. For a $24,000 contract, 10% = $2,400, but since $1,000 is less than $2,400, the maximum allowable down payment is $1,000. This statutory cap protects consumers from contractors who might take large upfront payments and abandon the project.

Why the Other Options Are Wrong

Option A: $2,400

$2,400 represents exactly 10% of the $24,000 contract price. While 10% is part of the calculation, B&P Code 7159 caps the down payment at the LESSER of 10% or $1,000. Since $2,400 exceeds the $1,000 cap, this amount is not legally permitted.

Option B: $7,200

$7,200 represents 30% of the contract price. There is no provision in B&P Code 7159 that permits a 30% down payment. This amount far exceeds the statutory limit and would expose the contractor to disciplinary action by the CSLB.

Option C: $4,800

$4,800 represents 20% of the contract price. Like $7,200, this amount has no basis in B&P Code 7159 and substantially exceeds both the 10% and $1,000 thresholds. Collecting this amount as a down payment would be a B&P Code violation.

Memory Technique

B&P 7159 down payment rule: '10% or $1,000—whichever is LESS.' For contracts over $10,000, the $1,000 cap always wins. For contracts under $10,000, the 10% wins. The magic threshold is $10,000: above it, the cap is $1,000.

Was this explanation helpful?

More California Questions

A homeowner signs a $15,000 home improvement contract on Monday at 2 PM at the contractor's office. Under California law, what is the latest time the homeowner can cancel the contract without penalty?

A swimming pool contract for $28,000 is signed on Wednesday at the customer's home. The contract includes proper cancellation notices. If the customer wants to cancel, they must do so by when?

Under California's prompt payment law, if a contractor submits a proper payment request to a property owner, payment is due within how many days?

A general contractor hires a subcontractor for $22,000. The general contractor receives payment from the owner but fails to pay the subcontractor within how many days, subjecting themselves to penalty interest?

Under California Civil Code Section 8180, when must a subcontractor serve a preliminary notice on a private work project?

Which of the following contracts is NOT subject to the 3-day right to cancel under California law?

A subcontractor completes roofing work on Tuesday, March 15th. The general contractor is paid by the owner on Friday, March 25th. Under California prompt payment laws, what is the latest date the general contractor must pay the subcontractor?

A contractor receives a progress payment of $18,000 from a property owner on Monday. The contractor owes subcontractors $12,000 of this amount. By what day must the contractor pay the subcontractors?

A swimming pool contractor enters into a $45,000 contract to install an in-ground pool. The contract includes a $5,000 down payment. What is the maximum down payment the contractor can legally collect under California law?

A contractor completes $15,000 worth of electrical work on a commercial building. The property owner disputes $3,000 of the charges. Under California prompt payment law, what amount must the owner pay within the required timeframe to avoid penalties?

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your contractor license exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.