Calculate the lien agent fee for a North Carolina construction project with a total contract value of $2,850,000. The fee structure is 0.10% of the first $1,000,000 and 0.05% of the remaining amount.

Correct Answer

D) $1,925

First $1,000,000 × 0.10% = $1,000. Remaining $1,850,000 × 0.05% = $925. Total = $1,000 + $925 = $1,925.

Answer Options
A
$2,425
B
$3,425
C
$2,925
D
$1,925

Why This Is the Correct Answer

The correct answer is D ($1,925). The tiered fee structure applies as follows: the first $1,000,000 × 0.10% = $1,000; the remaining $1,850,000 ($2,850,000 − $1,000,000) × 0.05% = $925. Total fee = $1,000 + $925 = $1,925.

Why the Other Options Are Wrong

Option A: $2,425

$2,425 is incorrect. This figure appears to result from applying 0.10% to the full $2,850,000 ($2,850) minus an incorrect adjustment, or from miscalculating the remaining balance. The tiered structure must be applied correctly with 0.10% only on the first million.

Option B: $3,425

$3,425 is incorrect. This may result from applying 0.10% to the entire $2,850,000 without using the tiered structure, or from adding an incorrect extra amount. Applying a flat 0.10% to the full contract value ignores the lower rate for amounts above $1,000,000.

Option C: $2,925

$2,925 is incorrect. This could result from applying 0.10% to the first $1,000,000 ($1,000) and then incorrectly applying 0.10% (instead of 0.05%) to only a portion of the remaining amount, or from some other arithmetic error. The correct rate for amounts above $1,000,000 is 0.05%, not 0.10%.

Memory Technique

Think '10 for the first million, 5 for the rest'—the rate halves after the first million. For $2.85M: first million = $1,000 (10 cents per thousand), remaining $1.85M = $925 (5 cents per thousand). Add them: $1,925.

Was this explanation helpful?

More North Carolina Questions

A residential contractor in NC wants to bid on a $125,000 project but currently holds an Intermediate license. What action must be taken?

A contractor discovers contaminated soil during excavation on a commercial project in Charlotte. Under NC environmental regulations, what is the first required action?

A North Carolina contractor completes a $45,000 residential addition project. The homeowner refuses to pay the final $8,000. What is the filing deadline for a mechanic's lien under NC lien law?

A residential contractor in Charlotte is building a deck addition. Which inspection is typically required first under NC building codes?

A contractor performs work on a residential property in North Carolina but is not paid. The work was completed on March 15th, and the last material was delivered on March 20th. What is the deadline to file a claim of lien?

A subcontractor performing electrical work discovers that the general contractor's license has been suspended. What action should the subcontractor take according to NC General Statutes?

A contractor in North Carolina discovers contaminated soil during excavation. The soil contains petroleum products above reportable levels. Which agency must be notified immediately?

A contractor performing work on a North Carolina highway project encounters a suspected archaeological artifact. What is the required action under NC environmental regulations?

Calculate the workers' compensation premium for a NC roofing contractor with $250,000 in annual payroll and a rate of $18.50 per $100 of payroll:

Calculate the lien amount a subcontractor can claim on a $180,000 project where they provided $35,000 in materials and labor, but the general contractor still owes them $12,000:

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your contractor license exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.