A roofing contractor discovers asbestos-containing materials during a renovation project in Winston-Salem. The area to be disturbed is 180 square feet. What is required under NC environmental regulations?
Correct Answer
B) Notification to NC DEQ and use of certified abatement contractor
NC environmental regulations require notification to NC DEQ and use of certified abatement contractors for asbestos disturbance regardless of area size.
Why This Is the Correct Answer
North Carolina environmental regulations, enforced by the NC Department of Environmental Quality (DEQ), require that any disturbance of asbestos-containing materials (ACM) triggers mandatory notification to NC DEQ and the use of a licensed, certified asbestos abatement contractor — regardless of the square footage involved. There is no minimum threshold that exempts a project from these requirements.
Why the Other Options Are Wrong
Option A: Owner notification only
Owner notification alone is insufficient. NC regulations require formal notification to the NC DEQ, not just informing the building owner. The owner must be informed, but the regulatory compliance obligation extends to state agency notification and certified abatement.
Option C: No special requirements for areas under 200 square feet
This is a dangerous misconception. NC asbestos regulations do not include a 200-square-foot exemption threshold. Any disturbance of ACM triggers abatement requirements. This option is factually incorrect and reflects federal NESHAP thresholds that do not apply here.
Option D: Simple disposal in regular construction waste
Asbestos-containing materials are classified as hazardous waste and cannot be disposed of in regular construction waste containers. Disposal requires transport by a licensed hauler to an approved disposal facility following strict EPA and NC DEQ procedures.
Memory Technique
Think: 'NC DEQ — No Cutoff for asbestos in NC.' Any size ACM disturbance = DEQ notification + certified contractor. Zero exceptions.
More North Carolina Questions
A residential contractor in NC wants to bid on a $125,000 project but currently holds an Intermediate license. What action must be taken?
A contractor discovers contaminated soil during excavation on a commercial project in Charlotte. Under NC environmental regulations, what is the first required action?
A North Carolina contractor completes a $45,000 residential addition project. The homeowner refuses to pay the final $8,000. What is the filing deadline for a mechanic's lien under NC lien law?
A residential contractor in Charlotte is building a deck addition. Which inspection is typically required first under NC building codes?
A contractor performs work on a residential property in North Carolina but is not paid. The work was completed on March 15th, and the last material was delivered on March 20th. What is the deadline to file a claim of lien?
A subcontractor performing electrical work discovers that the general contractor's license has been suspended. What action should the subcontractor take according to NC General Statutes?
A contractor in North Carolina discovers contaminated soil during excavation. The soil contains petroleum products above reportable levels. Which agency must be notified immediately?
A contractor performing work on a North Carolina highway project encounters a suspected archaeological artifact. What is the required action under NC environmental regulations?
Calculate the workers' compensation premium for a NC roofing contractor with $250,000 in annual payroll and a rate of $18.50 per $100 of payroll:
Calculate the lien amount a subcontractor can claim on a $180,000 project where they provided $35,000 in materials and labor, but the general contractor still owes them $12,000:
People Also Study
Business & Financial Management
120 questions · 70% to pass
Contract Administration
60 questions · 70% to pass
Project Management
60 questions · 70% to pass
Related Study Resources
Previous Question
A contractor has 15 employees with a total weekly payroll of $18,500. If the workers' compensation rate is $12.75 per $100 of payroll, what is the weekly premium?
Next Question
Calculate the lien agent fee for a North Carolina construction project with a total contract value of $2,850,000. The fee structure is 0.10% of the first $1,000,000 and 0.05% of the remaining amount.