Before filing a mechanics lien, what document must be served on the property owner within how many days of first furnishing labor or materials?
Correct Answer
B) Preliminary notice within 20 days
A preliminary notice must be served within 20 days of first furnishing labor or materials as a prerequisite to filing a mechanics lien.
Why This Is the Correct Answer
California Civil Code requires a preliminary notice to be served within 20 days of first furnishing labor or materials. This notice preserves the right to later file a mechanics lien if payment is not received. Without it, the claimant loses lien rights for work done before the notice was served.
Why the Other Options Are Wrong
Option A: Notice to owner within 30 days
Option A is wrong on two counts: the document type is correctly 'preliminary notice' (not 'notice to owner'), and the 30-day window is too long β the law specifies 20 days.
Option C: Notice to owner within 15 days
Option C uses the wrong document name ('notice to owner' instead of 'preliminary notice') and the wrong timeframe (15 days instead of 20). Both elements are incorrect.
Option D: Preliminary notice within 10 days
Option D gets the document name right ('preliminary notice') but states an incorrect 10-day window. The statutory deadline is 20 days from first furnishing.
Memory Technique
Think '20/20 vision to see your lien rights clearly' β you have 20 days to serve the preliminary notice. The word 'preliminary' means it comes before the lien, just as 20 comes before 30 and 15 in numerical order.
More California Questions
A homeowner signs a $15,000 home improvement contract on Monday at 2 PM at the contractor's office. Under California law, what is the latest time the homeowner can cancel the contract without penalty?
A swimming pool contract for $28,000 is signed on Wednesday at the customer's home. The contract includes proper cancellation notices. If the customer wants to cancel, they must do so by when?
Under California's prompt payment law, if a contractor submits a proper payment request to a property owner, payment is due within how many days?
A general contractor hires a subcontractor for $22,000. The general contractor receives payment from the owner but fails to pay the subcontractor within how many days, subjecting themselves to penalty interest?
Under California Civil Code Section 8180, when must a subcontractor serve a preliminary notice on a private work project?
Which of the following contracts is NOT subject to the 3-day right to cancel under California law?
A subcontractor completes roofing work on Tuesday, March 15th. The general contractor is paid by the owner on Friday, March 25th. Under California prompt payment laws, what is the latest date the general contractor must pay the subcontractor?
A contractor receives a progress payment of $18,000 from a property owner on Monday. The contractor owes subcontractors $12,000 of this amount. By what day must the contractor pay the subcontractors?
A swimming pool contractor enters into a $45,000 contract to install an in-ground pool. The contract includes a $5,000 down payment. What is the maximum down payment the contractor can legally collect under California law?
A contractor completes $15,000 worth of electrical work on a commercial building. The property owner disputes $3,000 of the charges. Under California prompt payment law, what amount must the owner pay within the required timeframe to avoid penalties?
People Also Study
Business & Financial Management
120 questions Β· 70% to pass
Contract Administration
60 questions Β· 70% to pass
Project Management
60 questions Β· 70% to pass
Related Study Resources
Previous Question
Which California Business and Professions Code section specifically governs service and repair contracts?
Next Question
A contractor completes $25,000 of electrical work on March 15th. The property owner fails to pay. What is the deadline for the contractor to record a mechanics lien under California Civil Code?