An original contractor fails to pay a subcontractor $8,400 for completed electrical work. The subcontractor gave proper preliminary notice. How long does the subcontractor have to file suit to enforce their mechanics lien after recording it?
Correct Answer
B) 90 days
Under Civil Code Section 8460, an action to enforce a mechanics lien must be commenced within 90 days after recording the lien.
Why This Is the Correct Answer
Under Civil Code Section 8460, a claimant must file suit to enforce a mechanics lien within 90 days after recording the lien. Missing this deadline causes the lien to become unenforceable, regardless of the underlying debt.
Why the Other Options Are Wrong
Option A: 1 year
1 year is the statute of limitations for many contract claims, but it does not apply to enforcing a recorded mechanics lien. The lien has its own strict 90-day enforcement window under Civil Code Section 8460.
Option C: 6 months
6 months is not the correct timeframe. This may be confused with other construction law deadlines, such as the time to record a lien after project completion, but it does not apply to enforcement after recording.
Option D: 60 days
60 days is too short. While 60 days appears in lien law (e.g., some recording deadlines), the suit to enforce after recording must be filed within 90 days, not 60.
Memory Technique
Record the lien, then you have 90 days to sue. Think: '3 months or lose it.' After recording, the clock ticks loudly β 90 days, then the lien dies.
More California Questions
A homeowner signs a $15,000 home improvement contract on Monday at 2 PM at the contractor's office. Under California law, what is the latest time the homeowner can cancel the contract without penalty?
A swimming pool contract for $28,000 is signed on Wednesday at the customer's home. The contract includes proper cancellation notices. If the customer wants to cancel, they must do so by when?
Under California's prompt payment law, if a contractor submits a proper payment request to a property owner, payment is due within how many days?
A general contractor hires a subcontractor for $22,000. The general contractor receives payment from the owner but fails to pay the subcontractor within how many days, subjecting themselves to penalty interest?
Under California Civil Code Section 8180, when must a subcontractor serve a preliminary notice on a private work project?
Which of the following contracts is NOT subject to the 3-day right to cancel under California law?
A subcontractor completes roofing work on Tuesday, March 15th. The general contractor is paid by the owner on Friday, March 25th. Under California prompt payment laws, what is the latest date the general contractor must pay the subcontractor?
A contractor receives a progress payment of $18,000 from a property owner on Monday. The contractor owes subcontractors $12,000 of this amount. By what day must the contractor pay the subcontractors?
A swimming pool contractor enters into a $45,000 contract to install an in-ground pool. The contract includes a $5,000 down payment. What is the maximum down payment the contractor can legally collect under California law?
A contractor completes $15,000 worth of electrical work on a commercial building. The property owner disputes $3,000 of the charges. Under California prompt payment law, what amount must the owner pay within the required timeframe to avoid penalties?
People Also Study
Business & Financial Management
120 questions Β· 70% to pass
Contract Administration
60 questions Β· 70% to pass
Project Management
60 questions Β· 70% to pass
Related Study Resources
Previous Question
A homeowner wants to cancel a $12,000 roofing contract signed at their home yesterday. The contractor has not yet started work. What must the homeowner do to properly exercise their cancellation rights?
Next Question
Which of the following contracts would be exempt from the written contract requirements under B&P Code 7159?