EstatePass
MichiganBuildermedium50% of exam part

According to Michigan Building Code, what is the minimum R-value for basement wall insulation in new construction?

Correct Answer

B) R-10 continuous or R-13 cavity

Michigan Energy Code allows either R-10 continuous insulation on basement walls or R-13 cavity insulation between framing members for Climate Zone 6A.

Answer Options
A
R-10 continuous
B
R-10 continuous or R-13 cavity
C
R-15 continuous
D
R-15 continuous or R-19 cavity

Why This Is the Correct Answer

Michigan falls in IECC Climate Zone 6A. The Michigan Energy Code allows two compliant approaches for basement wall insulation: R-10 continuous insulation (rigid foam or equivalent applied to the wall surface without gaps) OR R-13 cavity insulation (batts installed between framing members). Both approaches meet the code — the contractor may choose either method based on the construction approach.

Why the Other Options Are Wrong

Option A: R-10 continuous

R-10 continuous alone is a valid option but it is not the only option — the answer omits the equally valid R-13 cavity alternative. An answer that presents only one of two code-compliant paths is incomplete and therefore incorrect as a complete statement of the code requirement.

Option C: R-15 continuous

R-15 continuous insulation exceeds the Michigan Energy Code minimum for basement walls in Climate Zone 6A. While R-15 continuous would certainly pass, requiring it as the minimum overstates the code requirement and may lead to unnecessary cost.

Option D: R-15 continuous or R-19 cavity

R-15 continuous or R-19 cavity does not correspond to the Michigan Energy Code baseline for basement walls. These values are higher than required and reflect a misapplication of above-grade wall insulation requirements (which are more stringent) to basement walls.

Memory Technique

Basement walls in Michigan: R-10 continuous OR R-13 cavity. Remember it as '10 or 13 — below grade in Michigan.' Continuous insulation gets a lower R-value because it has no thermal bridging. Cavity insulation needs more R-value to compensate for stud bridging.

Was this explanation helpful?

More Michigan Questions

A residential foundation wall in Michigan is 8 feet high with 2 feet above grade. The backfill exerts lateral pressure of 30 psf per foot of depth. What is the maximum lateral pressure at the bottom of the foundation wall?

A builder discovers that the electrical service entrance was installed without proper permits. According to Michigan law, what is the most appropriate next step?

What is the maximum allowable span for a 2x8 floor joist (Grade 2 Douglas Fir) at 16" O.C. with 40 psf live load and 10 psf dead load according to Michigan Building Code span tables?

According to Michigan Building Code, what is the maximum height of a wood-framed bearing wall using 2x4 studs with standard construction?

A homeowner requests to convert a bedroom into a bathroom on the second floor. What is the primary Michigan code concern the builder must address?

According to Michigan plumbing regulations, what is the minimum pipe size required for a water service line serving a single-family residence?

A contractor is building a basement foundation wall that is 8 feet high and will retain 6 feet of soil. What is the minimum wall thickness required by the Michigan Building Code for poured concrete?

A homeowner wants to install a gas fireplace in their living room. The contractor notices the existing gas line is 1/2 inch black iron pipe. For a 40,000 BTU fireplace with a 25-foot run, is this pipe size adequate according to Michigan gas code?

During a framing inspection, the building official notes that the contractor used 2x4 studs at 24 inches on center for an exterior wall. According to Michigan Building Code, what is the maximum wall height allowed for this configuration?

A contractor is installing a beam to support floor joists. The beam must carry a total load of 8,000 pounds over a 12-foot span. If the allowable fiber stress for the lumber grade is 1,200 psi, what is the minimum required section modulus?

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your contractor license exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.