According to Florida lien law, how long does a contractor have to record a Claim of Lien after the last day of providing labor or materials?
Correct Answer
B) 90 days
Under Florida Statute Chapter 713, a contractor must record a Claim of Lien within 90 days after the last day they provided labor, services, or materials to the improvement.
Why This Is the Correct Answer
Florida Statute Chapter 713 specifically establishes that contractors must record their Claim of Lien within 90 days after the last day they provided labor, services, or materials to the improvement. This 90-day timeframe is a strict statutory requirement that cannot be extended or waived. Missing this deadline results in the complete loss of lien rights, making it one of the most critical deadlines in Florida construction law. The 90-day period begins running from the contractor's last day of work, not from project completion or final payment requests.
Why the Other Options Are Wrong
Option A: 120 days
60 days is too short and not the timeframe established by Florida Statute Chapter 713 for recording a Claim of Lien
Option D: 180 days
120 days exceeds the statutory timeframe and would result in loss of lien rights under Florida law
Memory Technique
Think '90 days to save your pay' - the 90-day deadline is your last chance to protect your right to payment through a lien
Reference Hint
Florida Statute Chapter 713 - Construction Liens, specifically Section 713.08
More Contract Admin Questions
A project experiences a 30-day delay due to unusually severe weather. The contract includes a liquidated damages clause of $1,000 per day for delays. If the weather delay is excusable but not compensable, what liquidated damages apply?
A commercial project requires a total of 12 inspections. The building department charges $85 per inspection for the first 5 inspections, $65 for inspections 6-10, and $45 for any additional inspections. What is the total inspection fee?
What document must be posted at the job site before a Certificate of Occupancy can be issued for a commercial building?
A mixed-use development requires a variance for reduced setbacks. The property is located within 500 feet of a hospital. What additional consideration must be addressed?
A LEED project requires tracking of regional materials. Materials are considered regional if they are extracted, harvested, or recovered, as well as manufactured within what distance of the project site?
An indemnification clause in a construction contract typically requires the contractor to:
A property owner wants to convert a single-family home into a duplex in an area zoned for single-family residential use. The conversion meets all building codes but violates density requirements. What approval is needed?
As-built drawings are typically required to be submitted:
AIA Document A401 is primarily used for:
A general contractor is building a 12,000 square foot commercial warehouse. The building permit fee is calculated at $8.50 per $1,000 of construction value. If the project value is $2,400,000, what is the building permit fee?
People Also Study
Business & Financial Management
120 questions Β· 70% to pass
Project Management
60 questions Β· 70% to pass
Related Study Resources
Previous Question
In a Guaranteed Maximum Price (GMP) contract, what happens to cost savings when the actual project costs are less than the GMP?
Next Question
A quality control inspection reveals that 15 out of 100 concrete test cylinders failed to meet specified strength requirements. What is the failure rate, and what action should be taken?
