EstatePass
Contract AdminProceduresmedium13% of exam part

A quality control inspection reveals that 15 out of 100 concrete test cylinders failed to meet specified strength requirements. What is the failure rate, and what action should be taken?

Correct Answer

B) 15% failure rate; investigate causes and potentially reject affected concrete

A 15% failure rate (15/100) is significant and unacceptable for concrete strength. This requires immediate investigation of causes and potential rejection of the affected concrete to maintain structural integrity.

Answer Options
A
15% failure rate; acceptable, no action needed
B
15% failure rate; investigate causes and potentially reject affected concrete
C
15% failure rate; reduce future testing frequency
D
85% failure rate; continue with construction

Why This Is the Correct Answer

Option B correctly identifies the 15% failure rate and prescribes the appropriate response. A 15% concrete strength failure rate significantly exceeds acceptable industry standards (typically 1-5% maximum). This level of failure indicates potential issues with mix design, placement, curing, or testing procedures that could compromise structural integrity. Immediate investigation and potential rejection of affected concrete is the only responsible course of action to ensure public safety and code compliance.

Why the Other Options Are Wrong

Option A: 15% failure rate; acceptable, no action needed

While the failure rate calculation is correct, reducing testing frequency when experiencing high failure rates is counterproductive and dangerous. Higher failure rates should trigger increased testing and quality control measures, not reduced oversight.

Option C: 15% failure rate; reduce future testing frequency

This option contains a fundamental mathematical error - the failure rate is 15% (15 failed out of 100), not 85%. Additionally, continuing construction with known concrete strength deficiencies would violate building codes and compromise structural safety.

Memory Technique

Remember 'FIFI' - Fifteen percent Failure Is Frightening, Investigate! Any concrete failure rate in double digits should trigger immediate concern and action.

Reference Hint

ACI 318 Building Code Requirements for Structural Concrete, Chapter 26 - Quality Control and Testing; Florida Building Code, Chapter 19 - Concrete

Was this explanation helpful?

More Contract Admin Questions

A project experiences a 30-day delay due to unusually severe weather. The contract includes a liquidated damages clause of $1,000 per day for delays. If the weather delay is excusable but not compensable, what liquidated damages apply?

A commercial project requires a total of 12 inspections. The building department charges $85 per inspection for the first 5 inspections, $65 for inspections 6-10, and $45 for any additional inspections. What is the total inspection fee?

What document must be posted at the job site before a Certificate of Occupancy can be issued for a commercial building?

A mixed-use development requires a variance for reduced setbacks. The property is located within 500 feet of a hospital. What additional consideration must be addressed?

A LEED project requires tracking of regional materials. Materials are considered regional if they are extracted, harvested, or recovered, as well as manufactured within what distance of the project site?

An indemnification clause in a construction contract typically requires the contractor to:

A property owner wants to convert a single-family home into a duplex in an area zoned for single-family residential use. The conversion meets all building codes but violates density requirements. What approval is needed?

As-built drawings are typically required to be submitted:

AIA Document A401 is primarily used for:

A general contractor is building a 12,000 square foot commercial warehouse. The building permit fee is calculated at $8.50 per $1,000 of construction value. If the project value is $2,400,000, what is the building permit fee?

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your Florida General Contractor exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.