A swimming pool contract for $55,000 includes a change order for additional equipment costing $8,000. The homeowner signs the change order at their residence on Thursday. What is the cancellation deadline for the change order?

Correct Answer

A) Monday at midnight

Change orders are subject to the same 3-day cancellation period as the original contract. Signed Thursday, deadline is Monday at midnight (3 business days).

Answer Options
A
Monday at midnight
B
Change orders are not subject to cancellation rights
C
Sunday at midnight
D
Friday at midnight

Why This Is the Correct Answer

Change orders signed at the homeowner's residence are subject to the same 3-business-day cancellation right as the original contract. Signed on Thursday, the three business days are Friday, Saturday (if it counts — but typically Saturdays count as business days under Civil Code 1689.5), and Monday. The deadline is midnight Monday. Under the Home Solicitation Sales Act, business days include Saturday, so: Day 1 = Friday, Day 2 = Saturday, Day 3 = Monday (Sunday is excluded). Cancellation deadline = midnight Monday.

Why the Other Options Are Wrong

Option B: Change orders are not subject to cancellation rights

Change orders signed at the homeowner's residence are not exempt from cancellation rights. The location of signing (the consumer's home) triggers the Home Solicitation Sales Act regardless of whether it is a new contract or a modification.

Option C: Sunday at midnight

Sunday at midnight would only be correct if Saturday were the third business day, but Sunday is excluded from the business day count. The three business days are Friday, Saturday, and Monday — making the deadline Monday midnight.

Option D: Friday at midnight

Friday at midnight would be only one business day after signing on Thursday — far short of the required three business days. This would deprive the homeowner of most of their cancellation window.

Memory Technique

Signed Thursday → start counting Friday. Count: Friday (1), Saturday (2), skip Sunday, Monday (3). Deadline = end of Monday. A simple calendar exercise: 'Skip Sunday, always.' Practice with different signing days before the exam.

Was this explanation helpful?

More California Questions

A homeowner signs a $15,000 home improvement contract on Monday at 2 PM at the contractor's office. Under California law, what is the latest time the homeowner can cancel the contract without penalty?

A swimming pool contract for $28,000 is signed on Wednesday at the customer's home. The contract includes proper cancellation notices. If the customer wants to cancel, they must do so by when?

Under California's prompt payment law, if a contractor submits a proper payment request to a property owner, payment is due within how many days?

A general contractor hires a subcontractor for $22,000. The general contractor receives payment from the owner but fails to pay the subcontractor within how many days, subjecting themselves to penalty interest?

Under California Civil Code Section 8180, when must a subcontractor serve a preliminary notice on a private work project?

Which of the following contracts is NOT subject to the 3-day right to cancel under California law?

A subcontractor completes roofing work on Tuesday, March 15th. The general contractor is paid by the owner on Friday, March 25th. Under California prompt payment laws, what is the latest date the general contractor must pay the subcontractor?

A contractor receives a progress payment of $18,000 from a property owner on Monday. The contractor owes subcontractors $12,000 of this amount. By what day must the contractor pay the subcontractors?

A swimming pool contractor enters into a $45,000 contract to install an in-ground pool. The contract includes a $5,000 down payment. What is the maximum down payment the contractor can legally collect under California law?

A contractor completes $15,000 worth of electrical work on a commercial building. The property owner disputes $3,000 of the charges. Under California prompt payment law, what amount must the owner pay within the required timeframe to avoid penalties?

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your contractor license exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.