A swimming pool contract for $45,000 includes a change order for additional decking costing $3,200. The original contract was signed at the customer's home on Tuesday. What is the customer's right to cancel the change order?
Correct Answer
B) 3 calendar days from signing the change order
Change orders to swimming pool contracts that increase the contract price by more than $1,000 are subject to the same 3-day right to cancel as the original contract.
Why This Is the Correct Answer
Option B is correct. Change orders to swimming pool contracts that increase the contract price by more than $1,000 carry the same 3-day right to cancel as the original contract. Critically, this period is measured in calendar days (not business days), running from the date the change order is signed. Since the $3,200 increase exceeds the $1,000 threshold, the full 3-calendar-day cancellation right applies.
Why the Other Options Are Wrong
Option A: 3 business days from signing the change order
Option A is incorrect. The 3-day cancellation period for swimming pool change orders is measured in calendar days, not business days. Business days would exclude weekends and holidays, making the effective window longer. California law specifically uses calendar days for this calculation.
Option C: No right to cancel change orders
Option C is incorrect. California law explicitly extends cancellation rights to change orders on swimming pool contracts when they increase the price by more than $1,000. The legislature recognized that significant change orders are functionally new contract commitments deserving the same consumer protection.
Option D: 7 calendar days from signing the change order
Option D is incorrect. There is no 7-day cancellation period under California contractor law for change orders or original swimming pool contracts. The statutory period is 3 calendar days. Seven days may be confused with other consumer protection laws (e.g., certain door-to-door sales in other contexts).
Memory Technique
Pool + Change Order over $1K = Same rules as original contract. Think: 'Big change, same protection.' And remember: Calendar days (count every day on the calendar, no exceptions).
More California Questions
A homeowner signs a $15,000 home improvement contract on Monday at 2 PM at the contractor's office. Under California law, what is the latest time the homeowner can cancel the contract without penalty?
A swimming pool contract for $28,000 is signed on Wednesday at the customer's home. The contract includes proper cancellation notices. If the customer wants to cancel, they must do so by when?
Under California's prompt payment law, if a contractor submits a proper payment request to a property owner, payment is due within how many days?
A general contractor hires a subcontractor for $22,000. The general contractor receives payment from the owner but fails to pay the subcontractor within how many days, subjecting themselves to penalty interest?
Under California Civil Code Section 8180, when must a subcontractor serve a preliminary notice on a private work project?
Which of the following contracts is NOT subject to the 3-day right to cancel under California law?
A subcontractor completes roofing work on Tuesday, March 15th. The general contractor is paid by the owner on Friday, March 25th. Under California prompt payment laws, what is the latest date the general contractor must pay the subcontractor?
A contractor receives a progress payment of $18,000 from a property owner on Monday. The contractor owes subcontractors $12,000 of this amount. By what day must the contractor pay the subcontractors?
A swimming pool contractor enters into a $45,000 contract to install an in-ground pool. The contract includes a $5,000 down payment. What is the maximum down payment the contractor can legally collect under California law?
A contractor completes $15,000 worth of electrical work on a commercial building. The property owner disputes $3,000 of the charges. Under California prompt payment law, what amount must the owner pay within the required timeframe to avoid penalties?
People Also Study
Business & Financial Management
120 questions Β· 70% to pass
Contract Administration
60 questions Β· 70% to pass
Project Management
60 questions Β· 70% to pass
Related Study Resources
Previous Question
A swimming pool contractor receives a $35,000 contract signed at the customer's home. The customer cancels within the 3-day period. What can the contractor legally retain?
Next Question
A swimming pool contractor's total contract price is $65,000. The contract allows for a down payment of $8,000. What is the maximum additional amount the contractor can request before starting work under California law?