A subcontractor provided materials worth $25,000 and labor worth $18,000 to a project. The general contractor paid $30,000. Under NRS 108, what is the maximum lien amount the subcontractor can claim?

Correct Answer

B) $13,000

The lien amount cannot exceed the amount due and owing. Total work = $43,000, amount paid = $30,000, so maximum lien = $43,000 - $30,000 = $13,000.

Answer Options
A
$18,000
B
$13,000
C
$43,000
D
$25,000

Why This Is the Correct Answer

The lien amount cannot exceed the amount due and owing. Total work = $43,000, amount paid = $30,000, so maximum lien = $43,000 - $30,000 = $13,000.

Was this explanation helpful?

More nv-supplement Questions

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your Florida General Contractor exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.