A Nevada contractor files a mechanics' lien for $45,000. What is the required bond amount to release this lien under NRS 108?
Correct Answer
B) $67,500
Under NRS 108, the bond amount to release a mechanics' lien must be 150% of the lien amount. $45,000 × 1.5 = $67,500.
Why This Is the Correct Answer
Under Nevada Revised Statutes (NRS) 108, the bond amount required to release a mechanics' lien must be 150% of the original lien amount. This provides additional security beyond the lien value to cover potential interest, costs, and attorney fees. For a $45,000 lien, the calculation is $45,000 × 1.5 = $67,500. This 150% requirement is standard practice in Nevada mechanics' lien law to ensure adequate protection for all parties involved.
Why the Other Options Are Wrong
Option A: $45,000
$112,500 represents 250% of the lien amount, which significantly exceeds the statutory requirement. This excessive bond amount would impose an unreasonable financial burden and is not mandated by NRS 108 for mechanics' lien release purposes.
Option D: $90,000
$90,000 represents 200% of the lien amount, which exceeds the statutory requirement under NRS 108. While this amount would be sufficient to release the lien, it is unnecessarily high and not required by Nevada law, making it an incorrect answer.
Memory Technique
Remember 'Nevada's Lien Release = 1.5 Times' or think 'One and a Half to Set it Free' - the bond must be 150% of the lien amount to release it in Nevada.
More nv-supplement Questions
Under NRS 624, what is the minimum net worth requirement for a Class A General Contractor license in Nevada?
According to Nevada building codes, which edition of the International Building Code (IBC) is currently adopted for commercial construction?
A contractor receives a Notice of Disciplinary Action from the NSCB. Within how many days can they request a hearing to contest the action?
Which Nevada building code edition is currently adopted for commercial construction in most Nevada jurisdictions?
What is the minimum net worth requirement for a Nevada Class A general contractor license?
A contractor's employee is injured on a Nevada job site. The contractor lacks workers' compensation insurance. What is the potential penalty under NRS 624?
Under Nevada law, a contractor's workers' compensation insurance policy lapses on June 1st, and they continue working until June 15th before renewing. What is the potential consequence?
A general contractor hires a subcontractor who injures a worker on site. The subcontractor has no workers' compensation insurance. Under Nevada law, who is primarily liable for the claim?
A Nevada contractor fails to carry required workers' compensation insurance. What penalty can the Nevada Industrial Insurance System impose per day of non-compliance?
A material supplier provides $28,000 worth of materials to a project. Under NRS 108, what is the deadline for filing a mechanic's lien if the project was completed on August 30th?
People Also Study
Business & Financial Management
120 questions · 70% to pass
Contract Administration
60 questions · 70% to pass
Project Management
60 questions · 70% to pass
