A material supplier provides $28,000 worth of materials to a project. Under NRS 108, what is the deadline for filing a mechanic's lien if the project was completed on August 30th?
Correct Answer
C) November 28th
Material suppliers must file mechanic's liens within 90 days of project completion under NRS 108. August 30th + 90 days = November 28th.
Why This Is the Correct Answer
Under Nevada Revised Statutes (NRS) 108, material suppliers must file a mechanic's lien within 90 days of project completion. When calculating from August 30th, counting 90 days forward brings us to November 28th. This is the absolute deadline for filing the lien to preserve the supplier's rights to secure payment for the $28,000 in materials provided.
Why the Other Options Are Wrong
Option A: October 30th
October 30th represents only 61 days from the August 30th completion date, which falls short of the required 90-day filing period under NRS 108. This would result in an untimely filing and loss of lien rights.
Option B: November 30th
November 30th exceeds the 90-day deadline by 2 days, making it 92 days from project completion. Filing after the statutory deadline would invalidate the mechanic's lien and forfeit the supplier's security interest.
Option D: September 30th
September 30th is only 31 days from the August 30th completion date, which is far too early and doesn't utilize the full 90-day period allowed under Nevada law for filing mechanic's liens.
Memory Technique
Remember '90 Days to Save' - material suppliers have exactly 90 days from project completion to file their mechanic's lien in Nevada, or they lose their security rights forever.
More nv-supplement Questions
Under NRS 624, what is the minimum net worth requirement for a Class A General Contractor license in Nevada?
A Nevada contractor files a mechanics' lien for $45,000. What is the required bond amount to release this lien under NRS 108?
According to Nevada building codes, which edition of the International Building Code (IBC) is currently adopted for commercial construction?
A contractor receives a Notice of Disciplinary Action from the NSCB. Within how many days can they request a hearing to contest the action?
Which Nevada building code edition is currently adopted for commercial construction in most Nevada jurisdictions?
What is the minimum net worth requirement for a Nevada Class A general contractor license?
A contractor's employee is injured on a Nevada job site. The contractor lacks workers' compensation insurance. What is the potential penalty under NRS 624?
Under Nevada law, a contractor's workers' compensation insurance policy lapses on June 1st, and they continue working until June 15th before renewing. What is the potential consequence?
A general contractor hires a subcontractor who injures a worker on site. The subcontractor has no workers' compensation insurance. Under Nevada law, who is primarily liable for the claim?
A Nevada contractor fails to carry required workers' compensation insurance. What penalty can the Nevada Industrial Insurance System impose per day of non-compliance?
People Also Study
Business & Financial Management
120 questions Β· 70% to pass
Contract Administration
60 questions Β· 70% to pass
Project Management
60 questions Β· 70% to pass
