A material supplier delivers $15,000 worth of concrete to a job site on May 1st. The project is completed May 30th, and a notice of completion is recorded June 5th. What is the deadline for the supplier to file a mechanic's lien?

Correct Answer

B) July 5th

Under NRS 108.226, when a notice of completion is recorded, mechanic's liens must be filed within 30 days of the recording date.

Answer Options
A
November 1st
B
July 5th
C
August 4th
D
August 30th

Why This Is the Correct Answer

Under NRS 108.226, when a notice of completion is recorded, mechanic's liens must be filed within 30 days of the recording date.

Was this explanation helpful?

More nv-supplement Questions

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your Florida General Contractor exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.