A subcontractor completes work on a North Carolina project on June 1st but is not paid by the general contractor. The project owner makes final payment to the general contractor on June 30th. When must the subcontractor serve a claim of lien to preserve lien rights?

Correct Answer

B) By September 29th

Subcontractors must serve claim of lien within 120 days after final payment to the general contractor. 120 days from June 30th is September 29th.

Answer Options
A
By August 30th
B
By September 29th
C
By October 30th
D
By November 29th

Why This Is the Correct Answer

The correct answer is B (by September 29th). Under North Carolina's lien law, subcontractors must serve a claim of lien on real property within 120 days after the date the last furnishing of labor or materials occurs — but critically, for subcontractors the clock runs from the date the owner makes final payment to the general contractor, not from when the subcontractor finished work. Final payment to the GC was June 30th. Adding 120 days: June 30 + 120 days = September 29th (June has 30 days: 0 days left in June; July = 31 days; August = 31 days; September = remaining 58 days → 30 + 31 + 31 + 28 = September 29).

Why the Other Options Are Wrong

Option A: By August 30th

August 30th is incorrect. This is approximately 61 days after June 30th, which is only half of the 120-day window. Selecting August 30th likely results from confusing the 120-day period with a 60-day period, or from counting from the subcontractor's completion date (June 1st) rather than the owner's final payment date (June 30th).

Option C: By October 30th

October 30th is incorrect. This would be 122 days after June 30th, which misses the deadline by 2 days — the lien would have expired. This error may arise from miscounting calendar days or incorrectly starting the count on July 1st instead of treating June 30th as day zero.

Option D: By November 29th

November 29th is incorrect. This is 152 days after June 30th, well beyond the 120-day limit. The lien rights would have been lost long before November. This error likely results from confusing the 120-day lien period with a different, longer statutory period.

Memory Technique

Remember: 'Sub's clock starts when the GC gets paid.' In NC, the subcontractor's 120-day lien window begins on the owner-to-GC final payment date. To count 120 days from June 30: add 4 months (June 30 → October 30) then subtract 31 days (October has 31 days, so go back to September 29). Alternatively: July (31) + August (31) + September (58 needed) = 31+31+28 = 90... recalculate carefully by adding exactly 120 days.

Was this explanation helpful?

More North Carolina Questions

A residential contractor in NC wants to bid on a $125,000 project but currently holds an Intermediate license. What action must be taken?

A contractor discovers contaminated soil during excavation on a commercial project in Charlotte. Under NC environmental regulations, what is the first required action?

A North Carolina contractor completes a $45,000 residential addition project. The homeowner refuses to pay the final $8,000. What is the filing deadline for a mechanic's lien under NC lien law?

A residential contractor in Charlotte is building a deck addition. Which inspection is typically required first under NC building codes?

A contractor performs work on a residential property in North Carolina but is not paid. The work was completed on March 15th, and the last material was delivered on March 20th. What is the deadline to file a claim of lien?

A subcontractor performing electrical work discovers that the general contractor's license has been suspended. What action should the subcontractor take according to NC General Statutes?

A contractor in North Carolina discovers contaminated soil during excavation. The soil contains petroleum products above reportable levels. Which agency must be notified immediately?

A contractor performing work on a North Carolina highway project encounters a suspected archaeological artifact. What is the required action under NC environmental regulations?

Calculate the workers' compensation premium for a NC roofing contractor with $250,000 in annual payroll and a rate of $18.50 per $100 of payroll:

Calculate the lien amount a subcontractor can claim on a $180,000 project where they provided $35,000 in materials and labor, but the general contractor still owes them $12,000:

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your contractor license exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.