A subcontractor completed work worth $25,000 on March 15th but was not paid by the general contractor. Under Michigan lien law, what is the last day to file a construction lien if the project was substantially completed on April 30th?

Correct Answer

D) July 30th

Michigan allows 90 days from substantial completion to file a construction lien. 90 days from April 30th is July 30th.

Answer Options
A
June 29th
B
August 29th
C
May 30th
D
July 30th

Why This Is the Correct Answer

Michigan allows 90 days from substantial completion to file a construction lien. 90 days from April 30th is July 30th.

Was this explanation helpful?

More mi-business Questions

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your Florida General Contractor exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.