Which of the following is NOT a requirement for maintaining a Michigan contractor license under LARA regulations?
Correct Answer
A) Monthly financial reporting
Monthly financial reporting is not required for Michigan contractor license maintenance. The other options are all required under LARA regulations.
Why This Is the Correct Answer
Monthly financial reporting is not required for Michigan contractor license maintenance. The other options are all required under LARA regulations.
More mi-business Questions
A Michigan contractor forms an S-Corporation. What is the maximum number of shareholders allowed?
A contractor's employee is injured on a job site in Michigan. The contractor's workers' compensation insurance has a $500 deductible per claim. The total medical costs are $12,500 and lost wages are $3,200. What is the contractor's out-of-pocket cost for this claim?
What is the minimum general liability insurance coverage amount required for Michigan residential builders?
Under Michigan Act 299, what is the consequence for a contractor who performs work outside the scope of their license classification?
A contractor discovers that a subcontractor has filed a construction lien against their project. The general contractor believes the lien is invalid. What is the primary legal mechanism to challenge the lien in Michigan?
Under Michigan Act 299, what happens if a contractor continues to work without a valid license after it expires?
Which of the following best describes the 'pay when paid' clause limitation under Michigan law?
A project has total costs of $180,000 including $75,000 labor and $105,000 materials. With workers compensation at 7.8% of labor costs and general liability at 0.4% of total costs, what are the combined insurance costs?
A Michigan contractor is forming an LLC. What is the minimum general liability insurance coverage required for residential builders under Michigan law?
Under Michigan Act 299, a contractor's license must be renewed every:
People Also Study
Business & Financial Management
120 questions Β· 70% to pass
Contract Administration
60 questions Β· 70% to pass
Project Management
60 questions Β· 70% to pass
Related Study Resources
Previous Question
A contractor receives a complaint filed with LARA regarding defective work. The contractor has insurance coverage of $500,000 general liability and $100,000 professional liability. The claim is for $75,000 in damages. Which insurance policy would primarily respond to this claim?
Next Question
A subcontractor completed work worth $25,000 on March 15th but was not paid by the general contractor. Under Michigan lien law, what is the last day to file a construction lien if the project was substantially completed on April 30th?