A subcontractor completed work on March 15th and was not paid. The general contractor recorded a notice of completion on March 20th. What is the deadline for the subcontractor to file a mechanics lien?
Correct Answer
B) April 19th
Subcontractors have 30 days after recording of notice of completion to file a mechanics lien. March 20th + 30 days = April 19th.
Why This Is the Correct Answer
Under California Civil Code Section 8414, a subcontractor must file a mechanics lien within 30 days after the owner records a Notice of Completion (or Notice of Cessation). The Notice of Completion was recorded on March 20th. Adding 30 days: March 20 + 30 days = April 19th. This is the correct deadline.
Why the Other Options Are Wrong
Option A: June 13th
June 13th would be approximately 90 days from the Notice of Completion. The 90-day window applies to the prime/general contractor β not to subcontractors or material suppliers. Subcontractors have a shorter 30-day window after a recorded Notice of Completion.
Option C: May 14th
May 14th is approximately 60 days from the Notice of Completion, or 30 days from when the subcontractor completed work (March 15th + 60 days). Neither calculation produces the correct deadline. The 30-day clock for subcontractors runs from the Notice of Completion recording date, not from when work was finished.
Option D: May 19th
May 19th is 60 days from the Notice of Completion recording date. This does not correspond to any standard lien deadline period. The correct periods are 30 days (subcontractors after Notice of Completion) or 90 days (prime contractor after Notice of Completion).
Memory Technique
Remember the deadline split: '30 for subs, 90 for prime.' When a Notice of Completion is recorded, subcontractors and suppliers get 30 days; the general contractor gets 90 days. Start the clock from the recording date, not the work completion date.
More California Questions
A homeowner signs a $15,000 home improvement contract on Monday at 2 PM at the contractor's office. Under California law, what is the latest time the homeowner can cancel the contract without penalty?
A swimming pool contract for $28,000 is signed on Wednesday at the customer's home. The contract includes proper cancellation notices. If the customer wants to cancel, they must do so by when?
Under California's prompt payment law, if a contractor submits a proper payment request to a property owner, payment is due within how many days?
A general contractor hires a subcontractor for $22,000. The general contractor receives payment from the owner but fails to pay the subcontractor within how many days, subjecting themselves to penalty interest?
Under California Civil Code Section 8180, when must a subcontractor serve a preliminary notice on a private work project?
Which of the following contracts is NOT subject to the 3-day right to cancel under California law?
A subcontractor completes roofing work on Tuesday, March 15th. The general contractor is paid by the owner on Friday, March 25th. Under California prompt payment laws, what is the latest date the general contractor must pay the subcontractor?
A contractor receives a progress payment of $18,000 from a property owner on Monday. The contractor owes subcontractors $12,000 of this amount. By what day must the contractor pay the subcontractors?
A swimming pool contractor enters into a $45,000 contract to install an in-ground pool. The contract includes a $5,000 down payment. What is the maximum down payment the contractor can legally collect under California law?
A contractor completes $15,000 worth of electrical work on a commercial building. The property owner disputes $3,000 of the charges. Under California prompt payment law, what amount must the owner pay within the required timeframe to avoid penalties?
People Also Study
Business & Financial Management
120 questions Β· 70% to pass
Contract Administration
60 questions Β· 70% to pass
Project Management
60 questions Β· 70% to pass
Related Study Resources
Previous Question
A contractor quotes $8,200 for kitchen remodeling work. The homeowner agrees and wants to start immediately. What must the contractor do before beginning work?
Next Question
A homeowner signs a $15,000 home improvement contract on Monday at 2 PM in their home. Under California law, what is the latest day and time they can cancel the contract without penalty?