A subcontractor completed electrical work on March 15th but the general contractor has not paid the $28,000 invoice. Under NC lien law, if the subcontractor wants to preserve lien rights, the latest date to file a claim of lien is:

Correct Answer

D) July 13th

Subcontractors have 120 days from completion of their work to file a lien claim. March 15 + 120 days = July 13th.

Answer Options
A
May 14th
B
June 13th
C
September 11th
D
July 13th

Why This Is the Correct Answer

Under NC GS § 44A-12, a subcontractor must file a claim of lien on real property within 120 days after the last furnishing of labor or materials. Starting from March 15, counting forward 120 days: March has 16 remaining days (15th to 31st), April = 30 days (46), May = 31 days (77), June = 30 days (107), July 13 = 13 more days → total = 120 days. Therefore July 13th is the deadline.

Why the Other Options Are Wrong

Option A: May 14th

May 14th is only 60 days from March 15th — exactly half the allowed window. This is the 60-day deadline that applies to notices of subcontract in some contexts, not the lien filing deadline.

Option B: June 13th

June 13th is 90 days from March 15th. This might be confused with the 90-day deadline used in some other states or for other notice requirements, but NC allows 120 days for lien claims.

Option C: September 11th

September 11th is approximately 180 days — far beyond the 120-day statutory limit. A lien filed this late would be invalid.

Memory Technique

120 days = 4 months. March 15 + 4 months = July 15, then subtract 2 days for the month-length adjustment = July 13. Or simply count: 16 (Mar) + 30 (Apr) + 31 (May) + 30 (Jun) + 13 (Jul) = 120.

Was this explanation helpful?

More North Carolina Questions

A residential contractor in NC wants to bid on a $125,000 project but currently holds an Intermediate license. What action must be taken?

A contractor discovers contaminated soil during excavation on a commercial project in Charlotte. Under NC environmental regulations, what is the first required action?

A North Carolina contractor completes a $45,000 residential addition project. The homeowner refuses to pay the final $8,000. What is the filing deadline for a mechanic's lien under NC lien law?

A residential contractor in Charlotte is building a deck addition. Which inspection is typically required first under NC building codes?

A contractor performs work on a residential property in North Carolina but is not paid. The work was completed on March 15th, and the last material was delivered on March 20th. What is the deadline to file a claim of lien?

A subcontractor performing electrical work discovers that the general contractor's license has been suspended. What action should the subcontractor take according to NC General Statutes?

A contractor in North Carolina discovers contaminated soil during excavation. The soil contains petroleum products above reportable levels. Which agency must be notified immediately?

A contractor performing work on a North Carolina highway project encounters a suspected archaeological artifact. What is the required action under NC environmental regulations?

Calculate the workers' compensation premium for a NC roofing contractor with $250,000 in annual payroll and a rate of $18.50 per $100 of payroll:

Calculate the lien amount a subcontractor can claim on a $180,000 project where they provided $35,000 in materials and labor, but the general contractor still owes them $12,000:

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your contractor license exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.