A general contractor in NC subcontracts electrical work to an unlicensed electrician for a commercial project. Under NC General Statutes Chapter 87, what is the potential consequence for the general contractor?
Correct Answer
C) License suspension or revocation
NC General Statutes Chapter 87 allows for license suspension or revocation when contractors use unlicensed subcontractors for work requiring licensure.
Why This Is the Correct Answer
Under NC General Statutes Chapter 87, engaging an unlicensed subcontractor for work that requires licensure is a serious violation that exposes the general contractor to license suspension or revocation. The licensing board treats this as professional misconduct that undermines the integrity of the licensing system.
Why the Other Options Are Wrong
Option A: Warning letter only
Option A ('Warning letter only') is incorrect. A warning letter alone is not an authorized consequence for knowingly using unlicensed subcontractors on licensed work under Chapter 87. The statute provides for more significant disciplinary actions.
Option B: Fine up to $1,000
Option B ('Fine up to $1,000') is incorrect. While fines can be part of disciplinary action, stating the consequence is limited to only a $1,000 fine understates the severity. The board's primary and most serious tool is license action, not a capped monetary penalty.
Option D: Mandatory retraining requirement
Option D ('Mandatory retraining requirement') is incorrect. NC Chapter 87 does not prescribe mandatory retraining as a standalone penalty for using unlicensed subcontractors. This is not among the enumerated disciplinary tools available to the NC Licensing Board for General Contractors.
Memory Technique
Remember: unlicensed = unlawful = un-licensed (for you too). If you hire someone without the proper license, YOU could lose YOUR license. The chain of accountability goes upward.
More North Carolina Questions
A residential contractor in NC wants to bid on a $125,000 project but currently holds an Intermediate license. What action must be taken?
A contractor discovers contaminated soil during excavation on a commercial project in Charlotte. Under NC environmental regulations, what is the first required action?
A North Carolina contractor completes a $45,000 residential addition project. The homeowner refuses to pay the final $8,000. What is the filing deadline for a mechanic's lien under NC lien law?
A residential contractor in Charlotte is building a deck addition. Which inspection is typically required first under NC building codes?
A contractor performs work on a residential property in North Carolina but is not paid. The work was completed on March 15th, and the last material was delivered on March 20th. What is the deadline to file a claim of lien?
A subcontractor performing electrical work discovers that the general contractor's license has been suspended. What action should the subcontractor take according to NC General Statutes?
A contractor in North Carolina discovers contaminated soil during excavation. The soil contains petroleum products above reportable levels. Which agency must be notified immediately?
A contractor performing work on a North Carolina highway project encounters a suspected archaeological artifact. What is the required action under NC environmental regulations?
Calculate the workers' compensation premium for a NC roofing contractor with $250,000 in annual payroll and a rate of $18.50 per $100 of payroll:
Calculate the lien amount a subcontractor can claim on a $180,000 project where they provided $35,000 in materials and labor, but the general contractor still owes them $12,000:
People Also Study
Business & Financial Management
120 questions Β· 70% to pass
Contract Administration
60 questions Β· 70% to pass
Project Management
60 questions Β· 70% to pass
Related Study Resources
Previous Question
Calculate the workers' compensation experience modification factor for a contractor with actual losses of $45,000 and expected losses of $60,000:
Next Question
A subcontractor completed electrical work on March 15th but the general contractor has not paid the $28,000 invoice. Under NC lien law, if the subcontractor wants to preserve lien rights, the latest date to file a claim of lien is: