A service and repair contract for HVAC maintenance totals $850. The work is performed at a commercial building. Which requirement applies under B&P Code 7159.5?
Correct Answer
B) Written contract required without cancellation notice
Since the contract exceeds $500, a written contract is required under B&P 7159.5. However, the 3-day cancellation right typically applies to residential, not commercial work.
Why This Is the Correct Answer
B&P Code 7159.5 governs service and repair contracts. For work exceeding $500, a written contract is required. However, the 3-day right to cancel (with the required cancellation notice) applies to residential transactions, not commercial ones. Since this is a commercial building, the written contract requirement applies but the 3-day cancellation notice does not.
Why the Other Options Are Wrong
Option A: No written contract required
No written contract is required is incorrect. Once a service or repair contract exceeds $500, a written contract is mandatory under B&P 7159.5. The $850 contract here clearly exceeds that threshold.
Option C: Written contract required with 3-day cancellation notice
Written contract with 3-day cancellation notice would be required for residential home improvement contracts over $500. The 3-day cancellation right is a consumer protection measure tied to residential transactions β commercial clients do not receive this statutory protection.
Option D: Verbal contract acceptable with written estimate
A verbal contract with a written estimate is not an acceptable substitute when the contract value exceeds $500. B&P 7159.5 requires an actual written contract, not just an estimate. The distinction between an estimate and a binding written contract is legally significant.
Memory Technique
Key distinction: '$500 threshold = written contract required for EVERYONE (residential and commercial). 3-day cancellation notice = RESIDENTIAL ONLY.' Commercial clients are sophisticated parties who do not get the same consumer protections as homeowners.
More California Questions
A homeowner signs a $15,000 home improvement contract on Monday at 2 PM at the contractor's office. Under California law, what is the latest time the homeowner can cancel the contract without penalty?
A swimming pool contract for $28,000 is signed on Wednesday at the customer's home. The contract includes proper cancellation notices. If the customer wants to cancel, they must do so by when?
Under California's prompt payment law, if a contractor submits a proper payment request to a property owner, payment is due within how many days?
A general contractor hires a subcontractor for $22,000. The general contractor receives payment from the owner but fails to pay the subcontractor within how many days, subjecting themselves to penalty interest?
Under California Civil Code Section 8180, when must a subcontractor serve a preliminary notice on a private work project?
Which of the following contracts is NOT subject to the 3-day right to cancel under California law?
A subcontractor completes roofing work on Tuesday, March 15th. The general contractor is paid by the owner on Friday, March 25th. Under California prompt payment laws, what is the latest date the general contractor must pay the subcontractor?
A contractor receives a progress payment of $18,000 from a property owner on Monday. The contractor owes subcontractors $12,000 of this amount. By what day must the contractor pay the subcontractors?
A swimming pool contractor enters into a $45,000 contract to install an in-ground pool. The contract includes a $5,000 down payment. What is the maximum down payment the contractor can legally collect under California law?
A contractor completes $15,000 worth of electrical work on a commercial building. The property owner disputes $3,000 of the charges. Under California prompt payment law, what amount must the owner pay within the required timeframe to avoid penalties?
People Also Study
Business & Financial Management
120 questions Β· 70% to pass
Contract Administration
60 questions Β· 70% to pass
Project Management
60 questions Β· 70% to pass
Related Study Resources
Previous Question
Under California Civil Code Section 8000 et seq., what is the deadline for a general contractor to file a mechanics lien on a private work project after completion of the work?
Next Question
A swimming pool contract for $28,000 is signed on Wednesday at the customer's home. The contract includes proper cancellation notices. If the customer wants to cancel, they must do so by when?