EstatePass
CaliforniaContractseasy20% of exam part

A service and repair contract for $1,850 must include which of the following under B&P Code 7159.5?

Correct Answer

C) Description of work to be performed

B&P Code 7159.5 requires service and repair contracts to include a description of the work to be performed, among other requirements.

Answer Options
A
Detailed material specifications
B
3-day right to cancel notice
C
Description of work to be performed
D
Completion bond information

Why This Is the Correct Answer

B&P Code Section 7159.5 governs service and repair contracts (generally under $750 for simple repairs, but the requirements apply to the category). A description of the work to be performed is a fundamental required element of any service and repair contract. The owner must know what work they are authorizing before signing. This is a basic consumer protection requirement that applies regardless of contract amount.

Why the Other Options Are Wrong

Option A: Detailed material specifications

Detailed material specifications are not specifically required under B&P Code 7159.5 for service and repair contracts. While specifications may be included for clarity, they are not a mandated element of the contract form under this section.

Option B: 3-day right to cancel notice

The 3-day right to cancel notice applies to home improvement contracts (B&P Code 7159) and home solicitation contracts, not to standard service and repair contracts under Section 7159.5. Service and repair work is typically urgent or time-sensitive, so the 3-day cancellation right does not apply in the same way.

Option D: Completion bond information

Completion bond information is not required in service and repair contracts under B&P Code 7159.5. Completion bonds are a separate contractual tool not mandated for this contract category.

Memory Technique

7159.5 = Service and Repair = 'What are you going to DO?' The description of work is the most basic question any contract must answer. If you can only remember one thing about 7159.5, remember: describe the work. Everything else is secondary.

Was this explanation helpful?

More California Questions

A homeowner signs a $15,000 home improvement contract on Monday at 2 PM at the contractor's office. Under California law, what is the latest time the homeowner can cancel the contract without penalty?

A swimming pool contract for $28,000 is signed on Wednesday at the customer's home. The contract includes proper cancellation notices. If the customer wants to cancel, they must do so by when?

Under California's prompt payment law, if a contractor submits a proper payment request to a property owner, payment is due within how many days?

A general contractor hires a subcontractor for $22,000. The general contractor receives payment from the owner but fails to pay the subcontractor within how many days, subjecting themselves to penalty interest?

Under California Civil Code Section 8180, when must a subcontractor serve a preliminary notice on a private work project?

Which of the following contracts is NOT subject to the 3-day right to cancel under California law?

A subcontractor completes roofing work on Tuesday, March 15th. The general contractor is paid by the owner on Friday, March 25th. Under California prompt payment laws, what is the latest date the general contractor must pay the subcontractor?

A contractor receives a progress payment of $18,000 from a property owner on Monday. The contractor owes subcontractors $12,000 of this amount. By what day must the contractor pay the subcontractors?

A swimming pool contractor enters into a $45,000 contract to install an in-ground pool. The contract includes a $5,000 down payment. What is the maximum down payment the contractor can legally collect under California law?

A contractor completes $15,000 worth of electrical work on a commercial building. The property owner disputes $3,000 of the charges. Under California prompt payment law, what amount must the owner pay within the required timeframe to avoid penalties?

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your contractor license exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.