A residential subdivision requires 15 building permits. The jurisdiction charges a plan review fee of $125 per permit plus a $50 administrative fee per application. If all permits are submitted together as one application, what is the total plan review cost?
Correct Answer
D) $1,925
The calculation is: (15 permits × $125) + $50 administrative fee = $1,875 + $50 = $1,925. Since all permits are submitted as one application, only one administrative fee is charged.
Why This Is the Correct Answer
The correct answer is B ($1,925) because the calculation properly accounts for both components of the fee structure. Each of the 15 permits requires a $125 plan review fee, totaling $1,875. Since all permits are submitted together as one application, only a single $50 administrative fee is charged, not 15 separate fees. The total is therefore $1,875 + $50 = $1,925.
Why the Other Options Are Wrong
Option A: $1,975
Option A ($1,875) only includes the plan review fees (15 × $125) but fails to include the required $50 administrative fee for the application.
Option C: $1,875
Option C ($2,625) incorrectly calculates the administrative fee as if each permit required a separate $50 fee (15 × $50 = $750), when only one administrative fee applies per application.
Memory Technique
Remember 'PER vs TOTAL': Plan review fees are PER permit, but administrative fees are TOTAL per application batch
Reference Hint
Florida Building Code Chapter 1 - Scope and Administration, specifically sections on permit fees and application procedures
More Contract Admin Questions
A project experiences a 30-day delay due to unusually severe weather. The contract includes a liquidated damages clause of $1,000 per day for delays. If the weather delay is excusable but not compensable, what liquidated damages apply?
A commercial project requires a total of 12 inspections. The building department charges $85 per inspection for the first 5 inspections, $65 for inspections 6-10, and $45 for any additional inspections. What is the total inspection fee?
What document must be posted at the job site before a Certificate of Occupancy can be issued for a commercial building?
A mixed-use development requires a variance for reduced setbacks. The property is located within 500 feet of a hospital. What additional consideration must be addressed?
A LEED project requires tracking of regional materials. Materials are considered regional if they are extracted, harvested, or recovered, as well as manufactured within what distance of the project site?
An indemnification clause in a construction contract typically requires the contractor to:
A property owner wants to convert a single-family home into a duplex in an area zoned for single-family residential use. The conversion meets all building codes but violates density requirements. What approval is needed?
As-built drawings are typically required to be submitted:
AIA Document A401 is primarily used for:
A general contractor is building a 12,000 square foot commercial warehouse. The building permit fee is calculated at $8.50 per $1,000 of construction value. If the project value is $2,400,000, what is the building permit fee?
People Also Study
Business & Financial Management
120 questions · 70% to pass
Project Management
60 questions · 70% to pass
Related Study Resources
Previous Question
What is the maximum monetary limit for work performed under a Registered General Contractor license in Florida?
Next Question
In a unit price contract for 5,000 linear feet of fencing at $28 per linear foot, the actual quantity installed was 5,450 linear feet. What is the total contract amount to be paid?
