EstatePass
Contract AdminPermitsmedium20% of exam part

A residential subdivision requires 15 building permits. The jurisdiction charges a plan review fee of $125 per permit plus a $50 administrative fee per application. If all permits are submitted together as one application, what is the total plan review cost?

Correct Answer

D) $1,925

The calculation is: (15 permits × $125) + $50 administrative fee = $1,875 + $50 = $1,925. Since all permits are submitted as one application, only one administrative fee is charged.

Answer Options
A
$1,975
B
$2,625
C
$1,875
D
$1,925

Why This Is the Correct Answer

The correct answer is B ($1,925) because the calculation properly accounts for both components of the fee structure. Each of the 15 permits requires a $125 plan review fee, totaling $1,875. Since all permits are submitted together as one application, only a single $50 administrative fee is charged, not 15 separate fees. The total is therefore $1,875 + $50 = $1,925.

Why the Other Options Are Wrong

Option A: $1,975

Option A ($1,875) only includes the plan review fees (15 × $125) but fails to include the required $50 administrative fee for the application.

Option C: $1,875

Option C ($2,625) incorrectly calculates the administrative fee as if each permit required a separate $50 fee (15 × $50 = $750), when only one administrative fee applies per application.

Memory Technique

Remember 'PER vs TOTAL': Plan review fees are PER permit, but administrative fees are TOTAL per application batch

Reference Hint

Florida Building Code Chapter 1 - Scope and Administration, specifically sections on permit fees and application procedures

Was this explanation helpful?

More Contract Admin Questions

A project experiences a 30-day delay due to unusually severe weather. The contract includes a liquidated damages clause of $1,000 per day for delays. If the weather delay is excusable but not compensable, what liquidated damages apply?

A commercial project requires a total of 12 inspections. The building department charges $85 per inspection for the first 5 inspections, $65 for inspections 6-10, and $45 for any additional inspections. What is the total inspection fee?

What document must be posted at the job site before a Certificate of Occupancy can be issued for a commercial building?

A mixed-use development requires a variance for reduced setbacks. The property is located within 500 feet of a hospital. What additional consideration must be addressed?

A LEED project requires tracking of regional materials. Materials are considered regional if they are extracted, harvested, or recovered, as well as manufactured within what distance of the project site?

An indemnification clause in a construction contract typically requires the contractor to:

A property owner wants to convert a single-family home into a duplex in an area zoned for single-family residential use. The conversion meets all building codes but violates density requirements. What approval is needed?

As-built drawings are typically required to be submitted:

AIA Document A401 is primarily used for:

A general contractor is building a 12,000 square foot commercial warehouse. The building permit fee is calculated at $8.50 per $1,000 of construction value. If the project value is $2,400,000, what is the building permit fee?

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your Florida General Contractor exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.