EstatePass
Contract AdminContractseasy40% of exam part

In a unit price contract for 5,000 linear feet of fencing at $28 per linear foot, the actual quantity installed was 5,450 linear feet. What is the total contract amount to be paid?

Correct Answer

C) $152,600

In unit price contracts, payment is based on actual quantities. The total is 5,450 linear feet × $28 per linear foot = $152,600, regardless of the original estimated quantity.

Answer Options
A
$147,300
B
$140,000
C
$152,600
D
$150,000

Why This Is the Correct Answer

In unit price contracts, the contractor is paid based on the actual quantities of work performed, not the original estimated quantities. The contract establishes a fixed unit price ($28 per linear foot), but the total payment adjusts based on actual installation. Since 5,450 linear feet were actually installed at $28 per foot, the total payment is $152,600. This protects both parties when quantities vary from estimates.

Why the Other Options Are Wrong

Option A: $147,300

This appears to be an arbitrary amount that doesn't correspond to either the estimated quantity calculation or the actual quantity calculation.

Option D: $150,000

This amount doesn't match any logical calculation using either the estimated or actual quantities with the given unit price.

Memory Technique

Remember 'ACTUAL PAYS' - in unit price contracts, you get paid for ACTUAL quantities installed, not estimated quantities.

Reference Hint

Florida Building Construction Standards - Contract Types and Payment Methods chapter, specifically Unit Price Contract provisions

Was this explanation helpful?

More Contract Admin Questions

A project experiences a 30-day delay due to unusually severe weather. The contract includes a liquidated damages clause of $1,000 per day for delays. If the weather delay is excusable but not compensable, what liquidated damages apply?

A commercial project requires a total of 12 inspections. The building department charges $85 per inspection for the first 5 inspections, $65 for inspections 6-10, and $45 for any additional inspections. What is the total inspection fee?

What document must be posted at the job site before a Certificate of Occupancy can be issued for a commercial building?

A mixed-use development requires a variance for reduced setbacks. The property is located within 500 feet of a hospital. What additional consideration must be addressed?

A LEED project requires tracking of regional materials. Materials are considered regional if they are extracted, harvested, or recovered, as well as manufactured within what distance of the project site?

An indemnification clause in a construction contract typically requires the contractor to:

A property owner wants to convert a single-family home into a duplex in an area zoned for single-family residential use. The conversion meets all building codes but violates density requirements. What approval is needed?

As-built drawings are typically required to be submitted:

AIA Document A401 is primarily used for:

A general contractor is building a 12,000 square foot commercial warehouse. The building permit fee is calculated at $8.50 per $1,000 of construction value. If the project value is $2,400,000, what is the building permit fee?

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your Florida General Contractor exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.