In a unit price contract for 5,000 linear feet of fencing at $28 per linear foot, the actual quantity installed was 5,450 linear feet. What is the total contract amount to be paid?
Correct Answer
C) $152,600
In unit price contracts, payment is based on actual quantities. The total is 5,450 linear feet × $28 per linear foot = $152,600, regardless of the original estimated quantity.
Why This Is the Correct Answer
In unit price contracts, the contractor is paid based on the actual quantities of work performed, not the original estimated quantities. The contract establishes a fixed unit price ($28 per linear foot), but the total payment adjusts based on actual installation. Since 5,450 linear feet were actually installed at $28 per foot, the total payment is $152,600. This protects both parties when quantities vary from estimates.
Why the Other Options Are Wrong
Option A: $147,300
This appears to be an arbitrary amount that doesn't correspond to either the estimated quantity calculation or the actual quantity calculation.
Option D: $150,000
This amount doesn't match any logical calculation using either the estimated or actual quantities with the given unit price.
Memory Technique
Remember 'ACTUAL PAYS' - in unit price contracts, you get paid for ACTUAL quantities installed, not estimated quantities.
Reference Hint
Florida Building Construction Standards - Contract Types and Payment Methods chapter, specifically Unit Price Contract provisions
More Contract Admin Questions
A project experiences a 30-day delay due to unusually severe weather. The contract includes a liquidated damages clause of $1,000 per day for delays. If the weather delay is excusable but not compensable, what liquidated damages apply?
A commercial project requires a total of 12 inspections. The building department charges $85 per inspection for the first 5 inspections, $65 for inspections 6-10, and $45 for any additional inspections. What is the total inspection fee?
What document must be posted at the job site before a Certificate of Occupancy can be issued for a commercial building?
A mixed-use development requires a variance for reduced setbacks. The property is located within 500 feet of a hospital. What additional consideration must be addressed?
A LEED project requires tracking of regional materials. Materials are considered regional if they are extracted, harvested, or recovered, as well as manufactured within what distance of the project site?
An indemnification clause in a construction contract typically requires the contractor to:
A property owner wants to convert a single-family home into a duplex in an area zoned for single-family residential use. The conversion meets all building codes but violates density requirements. What approval is needed?
As-built drawings are typically required to be submitted:
AIA Document A401 is primarily used for:
A general contractor is building a 12,000 square foot commercial warehouse. The building permit fee is calculated at $8.50 per $1,000 of construction value. If the project value is $2,400,000, what is the building permit fee?
People Also Study
Business & Financial Management
120 questions · 70% to pass
Project Management
60 questions · 70% to pass
Related Study Resources
Previous Question
A residential subdivision requires 15 building permits. The jurisdiction charges a plan review fee of $125 per permit plus a $50 administrative fee per application. If all permits are submitted together as one application, what is the total plan review cost?
Next Question
A payment application shows $125,000 of work completed this period. With 5% retainage, the contractor has $8,000 in stored materials, and there was a $3,000 deduction for previous overpayment. What is the net payment due?
